I N S T A L L A T I O N

PAD MOUNTING (SW470)

1. Layout the concrete pad (Figure 1).

IMPORTANT NOTE: The relative location of the operator to the fence and the gate is critical. Be sure that the measurements for operator mounting are taken from the centerline of the fence and of the gate hinge.

2.Locate electrical conduit, as required, prior to pouring concrete.

3.Pour concrete pad.

4.Bolt the (2) pad mount brackets to the bottom of the operator with the hardware provided.

5.Secure the operator to the concrete pad. It is very important that the operator be level and square to the gate.

Figure 2

1/2" red head bolts or anchors (4 required)

Figure 1

 

Hinge Pin

Fence

 

 

 

 

 

 

c

 

24"

9-3/4"

22-1/2"

1/2" Redhead

 

 

(4 required.)

 

 

 

8"

 

 

Concrete pad 18"x34" min.

 

 

Operator

 

 

Parallel Mount

 

 

 

Centerline

 

Gate

6"

8"

 

 

 

 

 

 

8"16"1/2" Redhead

 

18-3/4"

 

(4 required)

Concrete pad

 

 

 

18"x34" min.

 

 

 

 

22-1/2"

 

 

Profile of

 

 

 

Operator

 

 

 

SW470

 

 

 

Perpendicular

 

 

Perpendicular Mount

Using suitable hardware secure operator to L-bolts

Power and control wiring should be run in separate conduit

Concrete Pad

2" to 4" above grade

Depth required by local codes or below frost line

10