I N S T A L L A T I O N
PAD MOUNTING (SW470)
1. Layout the concrete pad (Figure 1).
IMPORTANT NOTE: The relative location of the operator to the fence and the gate is critical. Be sure that the measurements for operator mounting are taken from the centerline of the fence and of the gate hinge.
2.Locate electrical conduit, as required, prior to pouring concrete.
3.Pour concrete pad.
4.Bolt the (2) pad mount brackets to the bottom of the operator with the hardware provided.
5.Secure the operator to the concrete pad. It is very important that the operator be level and square to the gate.
Figure 2
1/2" red head bolts or anchors (4 required)
Figure 1
| Hinge Pin | Fence |
|
|
|
| |
|
| c |
|
24" | 1/2" Redhead | ||
|
| (4 required.) | |
|
|
| |
8" |
|
| Concrete pad 18"x34" min. |
|
| Operator |
|
| Parallel Mount |
| |
|
| Centerline |
|
Gate | 6" | 8" |
|
|
| ||
|
|
| 8"16"1/2" Redhead |
|
| (4 required) | |
Concrete pad |
|
|
|
18"x34" min. |
|
|
|
|
|
| |
Profile of |
|
|
|
Operator |
|
|
|
SW470 |
|
|
|
Perpendicular |
|
|
Perpendicular Mount
Using suitable hardware secure operator to
Power and control wiring should be run in separate conduit
Concrete Pad
2" to 4" above grade
Depth required by local codes or below frost line
10