CGCFTP

VENT-FREE PROPANE/LP GAS COMPACT FIREPLACE

INSTALLATION

Continued

4.Carefully disconnect green and white wires at their insulated connectors.

5.In top of the heater cabinet, locate the four mounting holes on the outer cas- ing. Align these four holes with those on the blower bracket assembly. Attach blower bracket assembly to the outer casing with 4 #10 screws provided (see Figure 18).

6.Route the wire harness through the hole in left side of baffle. Pull wire harness through lower opening above where the valve shield was removed. (see Figure 18).

7.Insert the 4 wire harness into one of the round holes in the rear of the valve cover shield and through the rectangular hole in the front of shield (see Figure 18).

8.Reconnect red wire to switch position 3. Reconnect blue wire to switch posi- tion 1. Reconnect green and white wires.

9. Install the switch plate on the valve

cover shield with 2 #10 screws provided

(see Figure 19). Reinstall the valve

cover shield. Route power cord out of

the cabinet by inserting it through the

bushing on the outer casing (see Fig-

ure 18). Plug fan kit into 120-Volt

grounded power supply and test opera-

tion. Note: When switch is in the

AUTO position, the fan will start after

the heater has run for a few moments.

The fan will continue to run for several

moments after the heater has been

turned off. When switch is in the ON

Wiring Routing

Blower BracketHole in Baffle

Assembly

Screw

Baffle

Wire

SwitchHarness

position, the fan will run until turned

to OFF. Reinstall upper louver assem-

bly and hood if previously removed,

(see Figure 16, page 11). Close lower

louver door.

Valve Cover

Shield

3 2 1

Blue

Switch

Plate

Power

Cord

Red

Wire

Switch

Plate

Screw

Figure 19 - Installing Switch Plate to Valve Cover Shield

Valve Cover Harness

Shield

Box Cover

Figure 18 - Installing Blower Bracket Assembly

12

107036

Page 12
Image 12
Desa CGCFTP installation manual Install the switch plate on the valve