8

PRE-INSTALLATION PREPARATION

Framing

Installing Transition Pipe and Starter Collar

PRE-INSTALLATION

PREPARATION

Continued

FRAMING

1.Frame appliance enclosure as illustrated in Figures 7 and 8.

Note: If a wall covering is used to line the enclosure, then all measurements must be from the surface of the covering.

2.Place the appliance into the framing and secure it.

Note: If appliance is to be raised above floor level, a platform must be built to support the appliance.

3.Install the supply line to the appliance using a 1/2" NPT black iron gas line terminating 2 5/16" above the bottom of the appli- ance. The gas line may be installed from either side or from the bottom of the appliance (see Figure 19, page 12).

4.Feed flexible gas line through one of three gas line conduit sleeve and repack insulation to cover any openings. Prepare the incom- ing gas line with teflon tape or pipe joint compound and hook-up incoming gas line to the flexible gas line.

Note: If 1/2" NPT black iron pipe does not mate with fitting at the end of flexible gas line, remove fitting and replace with a 37 degree flare 3/4"-12, 1/2" NPT (female) fitting.

WARNING: When finishing appliance, do not overlap combustible material onto the black front face. Brick, tile, or other noncombustible materials may be applied to the face provided that any gap is between the material used and the face is caulked with a noncombustible caulking.

These Dimensions Allow for a 3/4" Clearance at Sides and Back of Fireplace. However, 0" Clearance is Permitted

D

C

A

3/4" Clearance

Not Required

 

 

 

 

at Nailing

 

 

Flanges

 

 

B

 

M36(B,H)/VM36(B,H)

M42(B,H)/VM42(B,H)

A

24 1/2"(622.3mm)

27 9/16"(700.1mm)

B

73 7/8"(1876.4mm)

83 7/8"(2130.4mm)

C

52 3/16"(1326mm)

59 5/16"(1506.6mm)

D

17 1/4"(438.2mm)

19 1/2"(495.3mm)

 

 

 

Figure 8 - Corner Installation Guidelines

INSTALLING TRANSITION PIPE AND STARTER COLLAR

The transition pipe and starter collar shown in Figure 9 are supplied with the fireplace, unattached and ready for installation. Remove the starter collar and set aside. Slide the transition pipe over the vent collar and attach with a minimum of three screws. Replace the starter collar over the transition pipe and attach using four screws located on the leg stands (five used on the model M42). To install B-vent piping, slide the first piece of B-vent over the transition pipe and attach with a minimum of two screws.

 

 

A

 

B

 

 

C

 

 

M36(B,H)/VM36(B,H)

M42(B,H)/VM42(B,H)

A

40 3/8" (1020mm)

44 3/8" (1121mm)

B

21 3/8" (543mm)

23 1/8" (587mm)

C

41 1/4" (1048mm)

48 1/4" (1226mm)

Figure 7 - Rough Opening for Installing in Wall

B-Vent Piping

Starter Collar

Transition Pipe

Vent Collar

Figure 9 - Installing Transition Pipe and Starter Collar

For morevisit www..com

108795

Page 8
Image 8
Desa M42, VM36 installation manual Framing, Installing Transition Pipe and Starter Collar