2 – Electrical Operation

INSTALLATION (continued)

GREEN

RED

operate

 

 

this switch

observe these lights

GREEN RED AMBER

Figure 1-4. Standard controls and indicators.

2 – Electrical Operation

This procedure checks electrical operation of the ATS.

Be sure to close the enclosure door

before proceeding to prevent personal injury

in case of electrical system fault.

Transfer Test

The ATS should still be bypassed and isolated. Both normal and emergency sources must be available and the emergency source generator (if used) must be capable of being started; put engine starting control in automatic position. The Transfer Switch Connected to Normal light and the Normal Source Accepted light should be on.

1.Turn the Isolation Handle clockwise (approximately 7 turns) until the window shows TEST position.

NOTE: The engine generator may be signalled to start while turning the Isolation Handle. If emergency source is available, the ATS may operate to the emergency position. If it does, operate Retransfer Delay Bypass switch.

2.Perform steps 1–5 at right. Observe the status lights.

Black square means light is on.

White square means light is off.

3.Turn the Isolation Handle clockwise (approximately 16 turns) to the CONN (connected) position.

4.Push in the Bypass Handle and turn it counterclock- wise until the OPEN indicator shows green.

This completes the Functional Test of the ADTB.

1---4

Turn and hold Transfer Control switch clockwise to Transfer

1Test until the engine starts and runs (within 15 sec.). The Emergency Source Accepted light should come on.

Transfer switch CN opens and the Transfer Switch Connected

2to Normal light should go off and the Load Disconnect Active light should come on. Both CN & CE contacts are now open.

After the delay transition time delay, the CE Transfer switch will operate to the Emergency

3position. The Transfer Switch Connected To Emergency light should come on and Load Dis- connect Active light goes off.

Transfer switch will operate back to Normal position after Feature 3A time delay. For im- mediate retransfer turn Transfer

4Control counterclockwise to Retransfer Delay Bypass. The Transfer Switch Connected To Normal light should come on; Transfer Switch Connected to Emergency light should go off.

The engine–generator will stop after the Feature 2E time delay

5(unloaded running engine cool- down). The Emergency Source Accepted light should go off.

Load

Disconnect

Active

Load

Disconnect

Active

Load

Disconnect

Active

Load

Disconnect

Active

Load

Disconnect

Active

Page 5
Image 5
Emerson 7000 SERIES 7ADTB Electrical Operation, INSTALLATION continued, Transfer Test, Be sure to close the enclosure door