BYPASSING & ISOLATING
(continued)
ISOLATING THE ATS
Isolating is required before any service work can be performed on the automatic transfer switch (ATS). Refer
CONN
position window
to Figures
1.Bypass the closed automatic transfer switch contacts. See BYPASSING on page
Align position indicator. Do not leave the handle in an intermediate position.
2.Turn the Isolation Handle counterclockwise (approx. 16 turns) until window shows TEST. The ATS can be tested now without load interruption (see page
Bypass Switch | E |
Turn crank |
|
counter- |
|
clockwise | L |
until |
|
window |
|
shows |
|
TEST. |
|
| N |
Automatic Transfer | Switch |
Figure |
3.Continue turning Isolation Handle counterclockwise (approx. 7 turns) until the window shows ISOLATE.
Bypass Switch | E |
Turn crank |
|
counter- |
|
clockwise | L |
until |
|
window |
|
shows |
|
ISOLATE. |
|
| N |
Automatic Transfer Switch |
|
Figure |
|
4.Open the lower enclosure door. Pull out the side rail carriage then roll out the transfer switch. It can be safely inspected in this position. The transfer switch can also be removed for easier maintenance opera- tions.
TEST
ISOLATE
unfold crank
counterclockwise – draws out
transfer switching device
Figure
NOTE: In the TEST position the transfer switching device solenoid operator circuit is energized through secondary disconnects.
Hazardous voltage capable of causing
electrical shock, burns, or death;
do not touch any control circuit terminals.
Figure
and pulled out for inspection.
See page
Transfer Switch weighs
Use lifting device 607064 or other device capable of lifting this weight to avoid personal injury or equipment damage.