Enviro 2100 owner manual Installation, Total Bricks

Models: 2100

1 20
Download 20 pages 53.64 Kb
Page 14
Image 14
TOTAL BRICKS:

Installation

BRICK PLACEMENT:

COMPLETE THE STOVE AND SMOKE PIPE INSTALLATION BEFORE PLACING THESE BRICKS.

1.Place the bottom layers of the sides and back of the firebox.

2.Place the floor bricks. The spaces between the bricks will soon fill with ashes.

3.Finish the sides and back ready to accept the top, ceiling bricks.

4.On the right and left sides, leave the front top brick out and install this brick last. Start with a 3” wide brick first, lift this brick up and rest the brick on the center baffle plate and the top of the side bricks, make sure that it is slid all they way to the back of the stove. Place a full width brick next, and then place another full width brick on the top so that all the joints are staggered. Complete both sides of the ceiling bricks in this manner.

5.Install the last two bricks in the right and left side, uppermost front corners.

6.Make sure that all bricks are secure before starting a fire in this unit.

Remove the ceiling bricks and clean above them once a year. Replace any broken bricks. When replacing bricks use only Clayburn type fire bricks.

TOTAL BRICKS:

 

39 - Full size bricks

9” long x 41⁄2” wide x 1.25” thick

8

- Partial bricks

9” long x 3” wide x 11⁄4” thick

3

- Half brick

41⁄2 “ long x 41⁄2” wide x 11⁄4” thick

(22.9 cm long x 11.4 cm wide x 3.2 cm thick) (22.9 cm long x 7.6 cm wide 3.2 cm thick) (11.4 cm long x 11.4 cm wide x 3.2 cm thick)

14

Page 14
Image 14
Enviro 2100 owner manual Installation, Total Bricks