Verifying the Installation
This method is similar to activating real subscribers. In order to use this method the following preconditions have to be fulfilled:
•The PEM installation has succeeded
•The PEM configuration of the network has been done
•The servers in the network are running
•All registration has been transferred to the PEM
The Service Configuration Manager is used for this task.
Alternatively the Bulk Configuration Manager can be used instead of the Service Configuration Manager and may simplify the task of configuring an
Please refer to Local Craft Tool User’s Guide and the PEM User’s Guide for detailed information of how to use them.
Table 3 | Verification with the ECN320 Local Craft Tool | |
| Verification Activity | Comments |
|
| |
Perform continuity check on each line from | Best to perform after rewiring and | |
the Exchange MDF to the Line MDF | before installing nodes | |
|
| |
Verify that the green LED is lit on the IP | Green – The IP DSLAM has booted | |
DSLAMs |
| and received an IP address and SW |
|
| |
Verify (if possible) that the ECN320 switch | Active Ethernet connection is | |
port where the IP DSLAMs are connected, | verified | |
indicates active Ethernet connection |
| |
|
| |
Recommended to perform check on each | Testing the IP DSLAM functionality | |
ADSL line |
| |
|
| |
Recommended to perform continuity check | Test that the new installation has | |
on each POTS or ISDN line | not affected the old services | |
|
| |
Start the Status Manager and use the Flash | Test of the registration process | |
LEDs button to verify the MDF position of the |
| |
IP DSLAMs (verification of the registration) |
| |
|
|
|