CARTRIDGE CHANGE DETERMINATION

CARTRIDGE CHANGE DETERMINATION

Replace cartridges when capacity is reached, or when flow becomes inadequate, but at least annually. All cartridges on multiple cartridge systems should be changed at the same time. The Everpure Pressure Gauge or Everguard Low Pressure Alarm provides a quick and simple means of determining when the filter cartridge(s) should be changed. Installed on the outlet port of the filter, the gauge or Everguard LPA can be used to measure both dynamic (flowing) and static (line) pressure. The cartridge(s) should be changed when the pressure gauge needle is in the red area while equipment is in operation, and yet the needle shows adequate line pressure between cycles. Observe the needle during the next equipment on cycle. If the needle registers adequate pressure, it can be assumed that the temporary low-pressure condition was caused by a brief power failure or other incoming pressure disruption.

FLUSHING

For maximum life, all carbon filter cartridges must be flushed for five minutes at full flow before use. ALL NEW CARTRIDGES MUST BE FLUSHED AFTER EACH CARTRIDGE CHANGE BEFORE BEING PUT INTO SERVICE!

If the cartridges are new, have been properly flushed and both needle and follower register inadequate pressure, or the LPA is sounding, you may be experiencing inadequate water pressure or some restriction may exist in the inlet water line. In either case, the incoming water pressure must be improved to receive optimum filter life.

COMPLETE CARTRIDGE CHANGE INSTRUCTIONS CAN BE FOUND ON THE FILTER CARTRIDGE LABEL.

Not for residential use. For food service applications only.

PRESSURE GAUGES

Low Inlet

Adequate Inlet

Low Outlet

Adequate Outlet

Pressure

Pressure

Pressure

Pressure

CARTRIDGE CHANGE PROCEDURE

Everpure Carbon Filter Cartridge Change

1.Shut off power to equipment. Shut off inlet water ahead of system.

2.Open flushing valve to relieve pressure.

3.Hold head firmly and push upward. Turn cartridge to left until it stops.

4.Pull cartridge downward and out of head.

5.Hold head firmly. Align cartridge lug with label. Insert new cartridge firmly into head.

6.Turn cartridge right 90˚ until rotation stops.

7.Repeat steps 3-6 for remaining cartridges.

Flushing

8.With flushing valve fully open, open inlet water at full force for five minutes. Close flushing valve.

9.Turn on power to equipment

For installations in Massachusetts, the Commonwealth of Massachusetts Plumbing Code 248 CMR shall be adhered to. Consult your licensed plumber for installation of the system. This system and its installation must comply with state and local regulations.