INSTALLATION
Figure 2

INSTALLATION

1. Before installation, apply two beads of high temperature silicone sealant or equivalent around the bottom of the storm collar and 1 inch above the end of the Starkap™ body. (See Figure 2)

2. Insert the Starkap™ into the inside of the vent termination pipe, making sure the Starkap™ is seated against the storm collar. Fasten the Starkap™ to the vent termination pipe by

using three (3) sheet metal screws. Placement of the screws

should be approximately 1/2 inch from the end of the vent termination pipe. (See Figure 3) The heads of the screws should be covered with high temperature.

Figure 3