Feet

 

Four leveling feet have been included with your

mill/drill. However, we recommend bolting your

machine to a sturdy workbench.

 

Components and Hardware Needed:

Qty

Feet with Hex Nut M12-1.75

4

To install the feet on the mill/drill:

 

1.With the help of an assistant, tip the mill/drill back to gain access to the underside of the base and thread the feet into the threaded holes.

2.Place your precision level on the mill/drill table.

3.Adjust the hex nut(s) until the mill/drill is level side-to-side and front-to-back as shown in

Figure 6.

Hex Nut

Figure 6. Leveling the mill/drill.

-14-

Mounting to

 

Workbench

 

The Model G0463 should be bolted to a work-

bench to provide maximum rigidity and safety.

Components and Hardware Needed:

Qty

Hex Bolts M12-1.75 x (length as needed)

4

Flat Washers 12mm

8

Lock Washers 12mm

4

Hex Nuts M12-1.75

4

To mount the mill/drill to the workbench:

 

1.Determine the best position for the mill/drill on the workbench.

Note: For the best performance, make sure the cross feed and the longitudinal handwheels extend out beyond the edge of the table surface. This will allow unrestricted handwheel operation.

2.Mark your hole locations using the mounting holes in the base as a guide.

3.Drill the holes needed in the workbench.

4.Place a precision level on the mill/drill table and shim the mill/drill until it is level side-to- side and front-to-back.

5.Bolt the mill/drill to the workbench.

G0463 Small Mill/Drill

Page 16
Image 16
Grizzly G0463 Feet, Mounting to Workbench, Components and Hardware Needed Qty, To install the feet on the mill/drill