INSTALLATION INSTRUCTIONS KK-RLL
ROOF MOUNTED LOAD LIGHT
TOOLS REQUIRED: |
| |
Power drill | Safety goggles | |
Caulk gun with silicone | Wrench set | |
3/8” drill bit |
| |
HARDWARE SUPPLIED: |
| |
1 | Work Light with Double Lamp | |
2 | 5/16 | GSM34010 |
2 | GSM30017 | |
2 | 5/16” x 1 ½” Fender Washer | GSM31019 |
1 | 3/8” Plastic Grommet | GSM20003 |
1 | Light mounting Bracket | PRM97310 |
INSTALLATION INSTRUCTIONS:
Note: Mounting and wiring must be done prior to prisoner compartment installation.
1.Bolt light fixture to the mounting bracket. (End with 2” flange and one hole). Overall bracket size is 10 ½” long by 2” wide.
2.Position load light bracket in desired location on roof: Recommended location is to center light above door opening on side or rear of van. If there is a third brake light, position the work light over the third brake light not on top of light.
3.Mark and drill three (3) 3/8” diameter holes. Bolt the bracket assembly on with two (2) stainless steel
4.The 3rd 3/8” diameter hole is for the wire. Wire goes through the roof and the bracket. Insert 3/8” plastic grommet in the hole from inside van going outside. Run wire through the bracket and grommet. Silicone the hole.
5.Follow the attached wiring diagram for the standard
Note: See attached wiring diagram.
Note: If desired, light can be activated with a single pole single throw switch in the dash.