Image 24

Ensure that the site safety and security programs are properly administered.

Interface directly with the HP installation project manager to ensure clear lines of communication during the installation and commissioning processes.

Site planning

A comprehensive site plan assists with the site design (MEP) and ensures the best possible HP POD 40c G2 installation process. When creating a site plan, consider the following information:

HP POD 40c G2 site requirements detailed in this document

HP POD 40c G2 site preparation drawing package

HP POD 40c G2 readiness checklist ("HP POD 40c G2 site readiness checklist" on page 31)

HP POD 40c G2 installation (on page 24)

The HP team can assist you by answering questions and help to guiding you throughout the process.

HP POD 40c G2 installation

HP POD 40c G2 installation includes the following:

Installation equipment staging (on page 24)

HP POD 40c G2 lifting layout (on page 24)

HP POD 40c G2 storage requirements (on page 25)

Additional structures (on page 25)

Installation equipment staging

Staging for the following items must be identified and considered:

Truck and component staging

Installation equipment staging

Site traffic

Regulatory or local permits

HP POD 40c G2 lifting layout

When preparing a site plan, identify where to place the HP POD 40c G2 and the equipment used for assembly. The figure below shows the following locations on an HP POD 40c G2 assembly site:

HP POD 40c G2 location

Crane location