HP Performance Optimized Data Center (POD) 40c manual General water supply Description Sign-off

Models: Performance Optimized Data Center (POD) 40c

1 41
Download 41 pages 46.35 Kb
Page 33
Image 33

Item

Description

Sign-off

 

 

 

 

 

28

Verify the location of the EPO system external to the

 

 

 

powerhouses, if applicable.

 

 

29

Verify the location of the remote electronic monitoring system.

 

 

30

Verify that tie-downs and other AHJ-required facilities for the HP

 

 

 

POD 40c G2 and power containers are complete at least one

 

 

 

week prior to arrival of HP-provided equipment.

 

 

General water supply

 

 

 

 

 

Item

Description

Sign-off

 

 

 

 

 

1

Verify that the site drainage is complete, and the HP POD 40c

 

 

 

G2 is not in a drainage path or flood prone area. HP

 

 

 

recommends placing the HP POD 40c G2 on a raised site pad

 

 

 

to prevent water from entering the HP POD 40c G2.

 

 

2

Verify that the humidification water quality meets or exceeds

 

 

 

these standards, which are essentially drinking water

 

 

 

standards.

 

 

3

Verify the humidification water supply isolation valve is

 

 

 

installed for each POD.

 

 

Chilled water system

 

 

 

 

 

Item

Description

Sign-off

 

 

 

 

 

1

Verify the chilled water supply and return headers are

 

 

 

accessible, in the appropriate location, and 100 cm (4 in) in

 

 

 

diameter.

 

 

2

Verify that the chilled water supply temperature meets the

 

 

 

minimum POD chilled water supply temperature of 10°C

 

 

 

(50°F).

 

 

3

Verify that a sufficient chilled water flow rate is available.

 

 

4

If necessary, verify that the customer-required chilled water

 

 

 

return temperatures can be attained.

 

 

Power requirements

 

 

 

 

 

Item

Description

Sign-off

 

 

 

 

 

1

Verify that the short circuit analysis, arc flash, and circuit

 

 

 

breaker coordination studies are complete. Verify power work

 

 

 

is completed according to the approved conduit routing

 

 

 

drawings that show the exact routes, plan view, sections, and

 

 

 

elevations.

 

 

2

Verify that temporary site power for installation and

 

 

 

construction is planned and available, if applicable.

 

 

3

Verify that adequate site power exists per the HP POD 40c G2

 

 

 

requirements.

 

 

General

 

 

 

 

 

Item

Description

Sign-off

 

 

 

 

 

1

Verify the utility connection to the HP POD 40c G2 and any

 

 

 

required metering equipment.

 

 

2

Verify the third-party commissioning services that might be

 

 

 

required by the owner.

 

 

 

 

Appendix B: Preparing for delivery 33

Page 33
Image 33
HP Performance Optimized Data Center (POD) 40c General water supply Description Sign-off, General Description Sign-off