Item | Description |
| |
|
|
|
|
28 | Verify the location of the EPO system external to the |
|
|
| powerhouses, if applicable. |
|
|
29 | Verify the location of the remote electronic monitoring system. |
|
|
30 | Verify that |
|
|
| POD 40c G2 and power containers are complete at least one |
|
|
| week prior to arrival of |
|
|
General water supply |
|
| |
|
|
| |
Item | Description |
|
|
|
|
|
|
1 | Verify that the site drainage is complete, and the HP POD 40c |
|
|
| G2 is not in a drainage path or flood prone area. HP |
|
|
| recommends placing the HP POD 40c G2 on a raised site pad |
|
|
| to prevent water from entering the HP POD 40c G2. |
|
|
2 | Verify that the humidification water quality meets or exceeds |
|
|
| these standards, which are essentially drinking water |
|
|
| standards. |
|
|
3 | Verify the humidification water supply isolation valve is |
|
|
| installed for each POD. |
|
|
Chilled water system |
|
| |
|
|
| |
Item | Description |
|
|
|
|
|
|
1 | Verify the chilled water supply and return headers are |
|
|
| accessible, in the appropriate location, and 100 cm (4 in) in |
|
|
| diameter. |
|
|
2 | Verify that the chilled water supply temperature meets the |
|
|
| minimum POD chilled water supply temperature of 10°C |
|
|
| (50°F). |
|
|
3 | Verify that a sufficient chilled water flow rate is available. |
|
|
4 | If necessary, verify that the |
|
|
| return temperatures can be attained. |
|
|
Power requirements |
|
| |
|
|
| |
Item | Description |
|
|
|
|
|
|
1 | Verify that the short circuit analysis, arc flash, and circuit |
|
|
| breaker coordination studies are complete. Verify power work |
|
|
| is completed according to the approved conduit routing |
|
|
| drawings that show the exact routes, plan view, sections, and |
|
|
| elevations. |
|
|
2 | Verify that temporary site power for installation and |
|
|
| construction is planned and available, if applicable. |
|
|
3 | Verify that adequate site power exists per the HP POD 40c G2 |
|
|
| requirements. |
|
|
General |
|
| |
|
|
| |
Item | Description |
|
|
|
|
|
|
1 | Verify the utility connection to the HP POD 40c G2 and any |
|
|
| required metering equipment. |
|
|
2 | Verify the |
|
|
| required by the owner. |
|
|
|
| Appendix B: Preparing for delivery 33 |