![INSTALLATION](/images/new-backgrounds/77622/7762213x1.webp)
INSTALLATION
PLEASE READ ENTIRE INSTRUCTION BEFORE PROCEEDING
Calculation before Installation
To calculate installation, please refer to Table 1. (All calculation in inches.)
TABLE 1
A = Height of Floor to Ceiling
B = Height of Floor to Counter Top (Standard: 36”)
C = Preferred Height of Counter Top to Hood
Bottom (Recommended 27” to 30”)
D = Height of Hood
E = Height of Duct Cover [F – D]
F = Height of Hood Installation
[A – (B + C)]
SAFETY WARNING
HOOD MAY HAVE VERY SHARP EDGES; PLEASE WEAR PROTECTIVE GLOVES IF REMOVING ANY PARTS FOR INSTALLING, CLEANING OR SERVICING.
Preparation before Installation
NOTE: TO AVOID DAMAGE TO YOUR HOOD, PREVENT DEBRIS FROM ENTERING THE VENT OPENING.
-Decide the location of venting pipe from the hood to the outside. Refer to Figure 1.
-A straight, short venting run will allow the hood to perform more efficiently.
-Try to avoid as many transitions, elbows, and long run as possible. This may reduce the performance of the hood.
-Use duct tape to seal the joints between pipe sections.
-Temporarily wire the hood to test for proper operation before installing.
1.If necessary, prepare back wall frame with cross
framing lumber for secure installation. Using references in Table 1 and measurements on page 12, decide the level of the lumber. Refer to Figure 2.
Figure 1
Figure 2