b-27
OPERATION
b-27
POWER WAVE® C300
The Power Wave® C300 is now configured and
ready to weld in the synergic mode.
Adjustment of the SPD value from the set value
has the affect of adjusting trim or arc length.
To increase the arc length; increase the SPD
value at the Power Wave® C300 to a value
higher than the actual WFS.
Remember; do not change the WFS at the spool
gun.
• To decrease the arc length; decrease the SPD
value at the Power Wave® C300 to a value lower
than the actual WFS.
Remember: The dialed in SPD value at the Power
Wave® C300 does not control the WFS at the
spool gun. Rather, it is adjusting the Power
Wave® C300 synergic work point. Therefore,
adjusting the SPD value will not change your actu-
al WFS at the spool gun. WFS can only be
changed at the spool gun.
PuSh / PuLL OPERATION
• Set the idle roll pressure on the wire drive between
an indicator reading of 0-2. A recommended start
point is 1.5.
• Configure the machine for push/pull operation
(see
parameter P.17 in the Set-up Menu section).
• Depending on the weld mode, set the Voltage or
Trim at the Power Wave® C300 using the right con-
trol knob located on the upper case front panel.
• The Wire Feed Speed (WFS) is set using the control
knob on the Torch. The left control knob on the
Power Wave® C300 is inactive. The actual WFS
being set at the torch is displayed on the Power
Wave® C300.
• All weld parameters normally available for the active
weld mode are available during push-pull operation.
Refer to the Operation Section of this manual.