Adding or Removing Cabinet Hardware
6-82Add a Control Carrier (Add Duplication)
6
3. Select
Reset System
from the
Maintenance
menu.
4. Select

Shutd own

from the

Reset Sys tem

menu.
5. Unseat the LAN Gateway assembly from its b ackplane connecto rs.
Shut Down DEFINITY AUDIX System
1. If a DEFINITY A UDIX re side s in the PPN or an EPN (whe re PPN Por t
Carrier B will be relocated), shut d own the AUDIX and allow the disk to
completely spin d own. Refer to ‘‘DEFINITY AUDIX Power Procedures’’ on
page 6-141.
!WARNING:

Neglecting to shut d own an AUDIX assembly before powering d own

the system cabinet where it resides can damage the AUDIX disk.
2. Unseat the AUDIX assembly from its backp lane connectors.
Power Down Port Networks
1. At the PPN, set the main circuit breaker to OFF.
2. At an EPN (where PPN port carrier B will be relocated), set the main c ircuit
brea ker to OFF.
Remove Doors and Panels and Disconnect Cables
1. Remove the front door from the PPN cabinet.
2. With the cable retainer in front of you and the p art number visible, loca te
the slot that is almost vertical. (This slot is adjac ent to the part number.)
Insert a flat blade screwd river with a wide blade (1/4-inc h recommended)
into the slot, and twist. The retainer snap opens easily so that the cable
can be removed.
3. At the cabinet, dis connect previously lab eled cables assoc iated with the
carrier to be removed.
4. Remove the back doors from the c abinet.