INSTALLATION PROCEDURE
CHAPTER 3 INSTALLATION PROCEDURE
1. GENERAL
This chapter explains the procedures for installing the PBX, the Maintenance Administration Terminal (MAT),
Desk Consoles, and various types of terminal equipment (single line telephones, Dterms, Data Modules, etc.).
The procedures in this chapter are shown in Figure 3-1.
Before installing it, thoroughly read Section 2., “PRECAUTIONS BEFORE BEGINNING INSTALLATION”
and observe the precautions while performing the installation.
Figure 3-1 Scope of Installation Procedure
Paging/Announcement
Circuit Card
Related
Procedures
Installation Preparation-Basic Procedures
Assembly and Installation of the Module
Group
Cabling within the Module Group
Mounting of Covers and
Post-Installation Procedures
Refer to Chapter 7.
RECT/
BATT
Power & Ground Cabling
Power Equipment Installation
SMDR Interface
Maintenance
Administration
Terminal
Desk Console
CHAMP Connector
Cable Running
Cable Termination
Installation of MDF
ALM IND./TAS IND./External
Key Box
Digital Interface
Single-line TEL
C.O./Tie Line
Installation of Peripheral
Equipment
Note: Work procedures are explained in detail in each NAP. Refer to the procedures by number (NAP-200-
XXX).
(NAP-200-001, 002, 003)
(NAP-200-004, 005)
(NAP-200-014)
(NAP-200-013)
(NAP-200-009)
(NAP-200-010, 012)
(NAP-200-008)
(NAP-200-006)
(NAP-200-018)
(NAP-200-017)
(NAP-200-016)
(NAP-200-007)
(NAP-200-015)