CHAPTER 3 ND-71548 (E)
Page 40
Issue 2
INSTALLATION PROCEDURE
NAP-200-001
Sheet 2/2
Installation Preparation
Proper Locations:
• A dry and clean place.
• A place that is well ventilated.
• A sufficiently illuminated room. (200 lux at floor level).
• A location around which there are no obstructing objects,
thus allowing easy maintenance.
• A place where C.O. lines can be brought in, or local
cables can be brought up to the MDF easily.
• A place where communication and security ground can
be obtained as required
Confirmation of Power and
Ground Supply
Confirm AC voltage and current capacity.
Confirm that a Circuit Breaker (NFB) is provided
exclusively for the system.
Confirm that ground terminals are provided separately from
those of the power supply system.
Confirm that one main power is provided to connect the
IMG(s).
Check the Quantity of
Packages
Check the quantity of packages to see if there is a
discrepancy with the Packing List.
If any equipment is missing, report it to the supplier
immediately.
A
END
B