CHAPTER 3 ND-71548 (E)
Page 42
Issue 2
INSTALLATION PROCEDURE
1. WHEN SECURING THE PBX DIRECTLY ONTO THE FLOOR
NAP-200-002
Sheet 2/8
Marking, Leveling, and Drilling
START
Marking Referring to Figure 002-1, mark the holes for the
anchor bolts of the base unit.
Drilling Drill holes at the locations marked for base unit.
Cutting of Free-Access Floor Referring to Figure 002-2, cut the free-access floor at
the marked cable locations by using a jigsaw.
Leveling Measure the level of floor surface of the free-access
floor.
When it is not level, adjust the support of the free-
access floor until it is level.
END