ND-71548 (E) CHAPTER 3
Page 45
Issue 2
INSTALLATION PROCEDURE
2. WHEN SECURING THE PBX WITH THE SPECIAL STAND
NAP-200-002
Sheet 5/8
Marking, Leveling, and Drilling
START
Marking and Drilling of Special
Stand
Drill the Special Stand for securing the PBX.
(See Figure 002-3.)
Marking, Drilling and Cutting of
Free-Access Floor
Mark, drill, and cut the free-access floor according to
the size of the special stand to be used.
Installing the Special Stand Secure the special stand onto the floor.
(See Figure 002-4.)
Level Check Check the level of the special stand. If necessary,
adjust the level by inserting spacers beneath the stand.
END