Installing the Rack Kit

Every ARCvault 48 comes with a tray-style Rack Kit that allows you to easily install and remove the unit without having to engage side rails. The Rack Kit includes all mounting hardware.

WARNING: It is recommended that a mechanical lifter (or at least two people) be used to raise and align the unit to prevent injury during installation.

WARNING: Use care when inserting or removing an ARCvault unit into or out of a rack to prevent the accidental tipping of the unit causing damage or personal injury.

1.Locate and mark the holes for the rails and retaining screws:

a.Starting with the right front flange, at the bottom of the rack (or from the top of a previously mounted component), locate the first set (Figure 2) of three holes with equal gaps of 5/8 inch (1.6cm).

 

 

Retaining Screw

 

 

Hole Mark

 

 

Right

 

 

Front Flange

4U

 

 

 

 

Retaining Screw

 

5/8" (1.6cm)

Hole Mark

 

1/2" (1.3cm)

Top Rail
First

5/8" (1.6cm)

Hole Mark

Hole

 

 

Set

5/8" (1.6cm)

Bottom Rail

 

 

 

Hole Mark

 

 

950

 

 

0-C RA

Figure 2. Holes Used for Attaching Rack Kit Rails

b.Mark the top and bottom holes of the set for the rail screws.

c.Mark the second and eighth holes above the set for the retaining screws.

d.Repeat Steps a–cfor the left side.

2.Repeat Step 1 for the rear holes.

CAUTION: Be sure rear holes are horizontally in line with the front holes to assure the unit remains level.

3.Adjust the rail rear brackets to fit the rail inside the rack flanges:

a.Remove and retain the two adjustment nuts and washers on the right rail.

b.Move the rear bracket so that the PEM studs are in different slots (Figure 3) based on the rack size.

For a 36" rack, use the two front slots.

For a 30" rack, use the two center slots.

For a 24" rack, use the two rear slots.

Adjust Rear Bracket to Fit Front

RA -C 00 36

PEM Studs and Lock NutsFigure 3. Outside Rail Adjustment for 30” Rack

c.Loosely replace the retained washers and screws.

d.Repeat Steps a–cfor the left rail.

4.Using the eight SEMS screws and four bar nuts provided, attach the rails (Figure 4) inside the flanges:

NOTE: To ensure proper alignment, the bar nut corner notches must face outside, away from the rail.

a.Attach the right rail inside the marked locations (Figure 4) of the right front and right rear flanges.

b.Tighten the adjustment nuts.

c.Repeat Steps a–bfor the left rail.

Rear FlangesFront FlangesClip Nuts
Bar Nut

CR-

 

6900

 

A

Rail Adjustment NutsFigure 4. Attaching the Rack Kit Rails

5.Attach four clip-nutsto the holes marked on the front rack flanges for the retaining thumbscrews.

6.Lift the ARCvault unit and gently slide it into the rack until the front panel touches the rack.

7.Tighten the four retaining thumbscrews behind the doors to secure the unit to the rack.