Pelco Manual C1402M-B (2/98) 173.5 J-BOX INSTALLATION
For installations requiring full plenum rating, perform the following step:
Installations Requiring Conduit
When conduit must be run to the enclosure back box:
1. Attach the provided J-box to the top of the enclosure back box as shown in
Figure 11 using the supplied 6-32 screws.
2. Remove one of the knockouts from the J-box and attach the conduit to the
J-box (hardware not supplied).
3. Run the cabling through to the conduit.
4. Assemble the connector onto the end of the cable that is in the J-box, per
Section 3.4.
5. Place the J-box cover onto the J-box with two (2) 6-32 screws (supplied).
or
Installations Not Requiring Conduit
When conduit is not required at the enclosure back box:
1. Attach the provided J-box to the top of the enclosure back box as shown in
Figure 11 using the supplied 6-32 screws.
2. Remove the knockout from the edge of the J-box cover.
3. Run the assembled cable (see Section 3.4) into the J-box and place the cover
onto the J-box with the cable going through the knockout section of the cover.
Attach with 6-32 screws (supplied).