Fax: (800)
2. Product: Hi Delta® copper
2.2BOILERS A. General
1. The boiler(s) shall be fired with |
| gas at a rated input of |
| BTU/hr. |
2.The boiler(s) shall be CSA tested and certified with a minimum thermal efficiency of 87 percent at full fire.
3.The boiler(s) shall be ASME inspected and stamped and National Board registered for 160 PSIG working pressure, complete with a Manufacturer's Data Report.
4.The boiler(s) shall have a floor loading of 65 lbs. /square foot or less.
B.Heat Exchanger
1.The heat exchanger shall be of a
2.The heat exchanger shall be sealed to 160 PSIG rated
3.The low water volume heat exchanger shall be
4.The headers shall be secured to the tube sheet by stud bolts with flange nuts to permit inspection and maintenance without removal of external piping connections.
5.The heat exchanger shall incorporate “V” baffles between the tubes to ensure complete contact of the external tube surfaces with the products of combustion.
6.The boiler(s) shall be capable of operating at inlet water temperatures as low as 120°F without condensation.
7.The boiler(s) shall be designed to accommodate field changes of either left or right hand plumbing and electrical while leaving the tube bundle in place.
C.Burners
1.The tubular burners shall have multiport radial gas orifices, punched ports and slots, be capable of quiet ignition and extinction without flashback at the orifice, and be manufactured from
2.The burners will be supplied with a
D.Ignition Control System
1.The boiler(s) shall be equipped with a 100 percent safety shutdown system.
2.The ignition shall be Hot Surface Ignition type with full flame rectification by remote sensing separate from the ignition source, with a
3.The igniter will be located away from the water inlet to protect the device from condensation during startup.
4.The ignition control module shall include an LED that indicates six (6) individual diagnostic flash codes.
5.Two external viewing ports shall be provided, permitting visual observation of burner operation.
E.Gas Train
1.The boiler(s) shall have a firing/leak test valve and pressure test valve as required by
2.The boiler(s) shall have
3.Gas control trains shall have a redundant safety
F.Boiler Control
1.The following safety controls shall be provided:
a.High limit control
b.Flow switch, mounted and wired
c.____PSIG ASME pressure relief valve, piped by the installer to an approved drain
Project Name / Date | Division 23 52 33.13 - 2 |