c.Inlet temperature error
d.Sensor out of range
6.The controller shall have alarm contacts.
Q.Low Gas Supply Pressure Manifold
1.The boiler(s) shall be CSA certified for
R.TruSeal™ Direct Vent
1.The boiler(s) shall meet safety standards for direct vent equipment as noted by the 2006 Uniform Mechanical Code, section 1107.6, ASHRAE
2.3SOURCE QUALITY CONTROL
A.The boiler(s) shall be completely assembled, wired, and
B.The boiler(s) shall be furnished with the sales order, ASME Manufacturer’s Data Report, inspection sheet, wiring diagram, rating plate and Installation and Operating Manual.
PART 3 - EXECUTION
3.1INSTALLATION
A.Must comply with
1.Local, state, provincial, and national codes, laws, regulations and ordinances
2.National Fuel Gas Code, ANSI Z223.1/NFPA 54 – latest edition
3.National Electrical Code, ANSI/NFPA 70 – latest edition
4.Standard for Controls and Safety Devices for Automatically Fired Boilers, ANSI/ASME
5.Canada only: CAN/CSA B149 Installation Code and CSA C22.1 CEC Part I
6.Manufacturer’s installation instructions, including required service clearances and venting guidelines
B.Manufacturer’s representative to verify proper and complete installation.
3.2START-UP
A.Shall be performed by Raypak
B.Test during operation and adjust if necessary:
1.Safeties (2.2 - F)
2.Operating Controls (2.3)
3.Static and full load gas supply pressure
4.Gas manifold and blower air pressure
C.Submit copy of
3.3TRAINING
A.Provide
B.Schedule training at least seven days in advance.
END OF SECTION
Project Name / Date | Division 23 52 33.13 - 5 |