PLUMBING FOR WATER CONNECTIONS
HEATER
The RP 2100 heater requires water flow and positive pressure to fire and operate properly. It must therefore be installed downstream of the discharge side of the filter pump. A typical installation is plumbed as follows:
1.The inlet side of the filter is plumbed directly to the discharge side of the filter pump;
2.The outlet side of the filter is then plumbed to the inlet of the heater; and
3.The outlet of the heater is plumbed to the return line to the pool or spa. The pump, filter and heater are
thus plumbed in series.
Plumbing from the heater back to the pool must not have any valves or restriction that could prevent flow when the pump is operating.
CAUTION: An additional source of heated water, i.e. a solar system, must be connected to the main line ahead of the heater inlet pipe in order for it to act as the primary heat source. If the primary system provides adequate heat to maintain
Heater must be located so that any water leaks will not damage the structure of adjacent area. PVC pipe may be glued directly into header unions.
FLOW RATES
MODEL | PIPE SIZE | MIN.GPM | *MAX.GPM |
185 | 20 | 125 | |
265 | 25 | 125 | |
335 | 35 | 125 | |
405 | 40 | 125 |
*When flow rates exceed maximum GPM an external auxiliary bypass valve is required. See external bypass valve section for details.
POLYMER HEADERS
CONNECTIONS (POLYMER HEADER)
Before attaching the
INLET/OUTLET HEADER (Polymer)
Flange Gasket
Header Flange (CPVC)
Header Flange Nut
(CPVC)
Inlet
Fig. #2002.1
High temperature CPVC Header Flanges and header Flange Nuts are provided. If there is any possibility of back- siphoning when the pump stops, it is suggested that a check valve (or valves) also be installed in the system.