ASSEMBLY

Figure 3 FRAME TIE BAR ASSEMBLY

3a. Assemble Tie Bars (5) to Frame Angles (4) using 1/2" x 1-1/2" Bolts (10), 1/2" Lockwashers (19), and 1/2" Nuts (15).

3b. Assemble Tie Bars (5) to Pull Bar (3) using

3

1/2" x 2" Bolt (11), 1/2" Lockwasher (19), and 1/2" Nut (15).

3c. Tighten hardware from Step 2a.

4

11

5

19

15

10

19

15

(10)

(19)

(15)

(11)

Bolt, 1/2" x 1-1/2"

Lockwasher, 1/2"

Nut, 1/2"

Bolt, 1/2" x 2"

Qty. 2

Qty. 3

Qty. 3

Qty. 1

Figure 4 SPRING SHANK ASSEMBLY

4a. Assemble Spring Shanks (6) to Frame Angles (4) using 1/2" x 1-1/2" Bolts (10), Special Spacers (21), 1/2" Lockwashers (19), and 1/2" Nuts (15).

Ensure Spring Shanks are set to run straight in the direction of travel.

4b. When assembling for in-between row cultivation, the extra Spring Shank will be mounted in the center of the cultivator, using the same hole and hardware used to fasten Tie Bars (5) to Pull Bar (3), reference location (A) in illustration.

 

 

5

 

 

A

3

10

4

 

 

21

19

15 6

(10)

(19)

(15)

 

Bolt, 1/2" x 1-1/2"

Lockwasher, 1/2"

Nut, 1/2"

 

Qty. 6

Qty. 6

Qty. 6

(21)

 

 

 

 

 

 

Special Spacer

 

 

 

Qty. 6 (or 7)

1007076 Rev. A

 

6

 

Page 6
Image 6
Sears CC-560 manual Frame TIE BAR Assembly