SECTION 2: BOILER INSTALLATION

STEP 1: LOCATING AND SETTING THE BOILER

PROCEDURE A: Check that provisions for combustion air are in accordance with National Fuel Gas Code ANSI Z223.1-latest edition and all applicable local codes. In Canada, follow CAN/CGA B149(.1 or .2) installation codes.

PROCEDURE B:

 

 

FIGURE 2.1

 

 

 

Check minimum

6"

6"

 

clearances to

 

 

 

 

combustibles are

 

 

 

proper as shown. Local

 

VENT DAMPER

 

requirements may

 

 

 

* TOP

 

specify greater

 

 

 

clearances & must be

 

 

 

adhered to.

 

 

 

Boiler shall be install-

18"

12"

12"

ed such that the gas

 

RECOMMEND

 

ignition system com-

 

MORE FOR

 

 

ACCESS TO

 

ponents are protected

 

VENT DAMPER

 

 

POSITION

 

from water (dripping,

 

INDICATOR

 

 

 

 

spraying, rain, etc.)

 

 

 

during appliance oper-

 

 

 

ation and service.

 

 

 

 

 

* 52" FOR GB250-S-5L THRU GB250 S-7

 

 

 

58" FOR GB250-S-8 THRU GB250-S-9

 

WARNING: Never install boiler on combustible flooring without combustible flooring pan or on carpeting as heat damage and/or fire may result.

CAUTION: Locate boiler so horizontal connecting flue pipe is as short as possible. Maximize height of vertical flue connector.

NOTE: Do not loosen tie rods on absorption unit. They accommodate thermal expansion. Loss of boiler structural integrity and water leaks/damage may result.

Step 1 Continued On Next Page