5.2M-2001 Checkout Procedure
NOTE: This test of the
1.Apply 120.0 V ac to
2.Connect neutral to
3.Verify local voltage y input voltage ±0.3 V.
4.Apply 100.0 mA
5.Verify UP, DOWN and ENTER buttons work.
—Checkout Procedure Complete—
5.3In-Service Test
1.Set the
2.Press ENTER.
3.Use UP and DOWN buttons to cause RAISE and LOWER outputs.
—In-Service Test Complete—
Return unit to desired settings6.0Checkout Procedure
NOTE: All Beckwith Electric units are fully calibrated at the factory.There is no need to
Set the AUTO/OFF/MANUAL switch to OFF. Inspect the MOTOR POWER and VOLTAGE fuses to ensure they are correctly sized and have not blown.
6.1Power
1.Remove any external connection between
8 WARNING: Voltage applied at the METER OUT test terminal may energize the regulator or transformer to a high voltage through the voltage transformer.
Death or severe electrical shock can occur.Do not connect any voltage source at the METER OUT test terminal.2.Connect a voltmeter to the METER OUT test terminal on the front of the adapter panel. 120 V ac should be indicated.
▲CAUTION: Do not reverse the ground and hot wires when connecting an external source. A 3 AG fuse (F2) is installed to protect the relay from dam- age if these connections are accidentally reversed. Spare fuses are supplied inside the fuse holders. Units returned with only a blown fuse are not cov- ered by warranty, and a nominal repair charge will be made for replacement of the fuse. Please check the fuse before returning the unit for repair, in order to avoid unnecessary repair charges.