IBM q5-44-3974-04 manual Additional Planning Tasks, You Must, Use

Page 23

5. Schedule the installation of electrical wiring and outlets.

6. Ensure that required host system updates are installed.

7.Begin installing and testing the Advanced Function Presentation lice programs and updates on the host system.

Step Three–Review Progress of Site Preparation

1.Review site-preparation progress with the IBM installation planning representative.

2. Ensure that the electrical wiring and outlets are being installe

3.Ensure that the attachment lines and equipment is being installed schedule.

Step Four–Ensure that Site Preparation is Complete

1.Ensure that installation and testing of electrical wiring and out complete.

2. Ensure that all site preparation activity is complete.

3.Gather information for the configuration work sheets in Chapter 5 “Configuring the 3130” on page 25 and schedule an NCP Generation needed.

 

Important

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Before

the

customer

engineer can install

the

3130,

you

must

 

 

 

complete

a configuration worksheet for the attachment

you

plan

to

 

 

 

use .

Completing the attachment worksheets usually requires input

the

personnel

responsible for

network

and

device driver

configu

For detailed worksheets, instructions, and examples,IBM

refer to

InfoPrint 60; 3130, 3160, and 3935 Advanced Function Printer:

Attachment Configuration Handbook, S544-3977.

If

you do not have a

copy

of

the

handbook, ask

your marketing

representative

to obt

for you. Information is also available on the Internet at

http://can.ibm.com/ibmprinters.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Step Five–Arrival of the 3130

1. Contact the customer engineer and arrange to have the 3130 in

2. Arrange to have the 3130 attached to the host system.

3.Complete tests of the Advanced Function Presentation licensed pro including the IBM-supplied installation verification procedures.

Additional Planning Tasks

Here are some other issues to consider before you install the 313

ŸTraining. Who will need training on the 3130 and AFP? Who will conduct

training sessions? When will training be scheduled?

ŸImplementation. How will the 3130 be phased into production? Which applications will use the 3130 first?

Chapter 2. Planning Overview11

Image 23
Contents Introduction and Planning Guide IBMIBM Fifth Edition SeptemberContents Dbcs 3130Set IBMAppendix B. Software and Hardware Requirements AIXPlugs IndexPage Federal Communications FCC StatementCommunication Statements CommissionEmvg AvisMinistère Des StatementTrademark Company TrademarksPresentation Printer Information, G544-3290 Attachment ConfigurationRelated Publications 60 3130, 3160, and 3935 Advanced Function PrinterWhats New in This Release Page General Description Advanced FunctionPrinter High-capacity Simplex 02S ModelsModel Model Number Comes Standard with This Simplex 01SDuplex 02D Optional FeaturesCommon Highlights Ipds Application Environment Optional FeaturesFeature Host EnvironmentsLPR FTP Tftp Operational Capabilities3130 Advanced Function Printer Users forGuide details Sdlc TCP/IP SystemLevels Data SecurityFonts Toner CartridgeAdvanced Function Image Object Document Content Architecture, SC31Reference-6802Only Guide for Minute Paper Sizes Size Chapter Overview Planning OverviewSite Implementation PlanStep Two-Review Use Attachment Configuration Handbook , S544-3977Additional Planning Tasks 3130 You MustPage Performance Considerations Processing EnvironmentHoles Compatibility ConsiderationsAttachments ProgramsGoca Objects ConversionIPDS-Only Ioca Images and IM ImagesGuide Definitions and Form DefinitionsBar Codes SystemDDS Overlay Generation Language/370Box Draw Function FontsPCL Other Font ConsiderationsRAM Ventilation Environmental Requirements Temperature and HumidityPreparing the Physical Environment Altitude RangeLevel Power RequirementsPower Dissipation Sound LevelsMode Physical Requirements Weight and DimensionsService Clearances Physical Layout and Space Requirements25.75 Installation RequirementsService Clearances ValuesPhysical Installation Worksheet Physical Installation WorksheetPage In3130 Advanced Function Printer Users Guide ConfiguringPrinter Configuration Worksheet 3160System Attachments Other Configuration ConsiderationsData Stream Configurations Font ManagementSdlc SNA Attachment Twinaxial AttachmentEthernet TCP/IP and NetWare Attachment Attachment PC Parallel AttachmentPart Number Replace Every Ordering and Storing SuppliesPrinter Supplies Ordering SuppliesSelecting Paper Feed Orientation Imp per Minute Paper ParametersParameter Label ParametersPrepunched Paper To theAdvanced Function Printer Cut-Sheet Paper .ReferencePrepunched Paper Clearances -- A4, B5, and Letter Size Paper CassettesEnvelopes Preprinted PaperDimensions Humidity TemperatureStoring Paper and Supplies Printer Cut-Sheet Paper Reference , yourLists Code Pages that correspond Each Appendix a Font SetLists Type Faces Arabic SymbolsCyrillic Greek Lists Code pages Used With IBM Core Interchange Lists ValidSubsets For each ListedLatin 4/5 Hebrew Width AltFont PitchAlt Pitch Point Font Code Other Resident Fonts IPDS-OnlyAlt Point Font Size WidthProvides an explanation Groups As used in the Code Pa Dbcs Resident Raster Font Set IPDS-Only Gcsgid SubsetsSize Box PointScalable Font Set Following Tables List ScalableRes Korean Dbcs Resident Scalable Code Page SetCharacter Set TypefaceSubsets Result Native OfficeVision IPDS-OnlyAS/400 Bolding Function Cyrillic Greek 2 of 2. IBM Core Interchange Resident Scalable Font SetFont Name used in PostScript Programs Full PostScript Resident Font SetType Fonts APL2 Font Name used in PostScript Programs Duplicate Type 1 FontsType 42 Fonts Font Type This Font Set is availableOutline 300 pel Only Font Type Symbol Set Set ID SupportLanguage SymbolWindows Latin 12J MC Text Multilingual 19M Symbol 579L PCL5e Language SupportTCP/IP Appendix B. Software and Hardware RequirementsData Stream SNAToken-Ring SNA ConsiderationsRisc SystemNovell NetWare VM SupportSystem Other SupportHost Support NotesFollowing workstation software supports the 3130 with JES3 PSF/MVS SupportPSF/VSE Support CPI PSF/VM SupportPSF For OS/400 Support Host Print Transforms for OS/400System Test Advanced Function Printer Attachment Configuration HandbookPSF/2 Support ForIeee Cabling System Technical Interface ,Specification GA27-3773Ethernet Network Attachment NetWare attachment,IBM InfoPrint see 60 3130PSF Support Summary PSF/VM CPU Attachment HardwareRisc Appendix B. Software and Hardware Requirements Ipds PCL-5e and PostScript Support Notes PSF/MVS Support PSF/VM Support PSF/2 Support Ethernet Network Attachment PSF Support Summary PSF/VM Attachment Hardware Risc Title Number BibliographySystem/370 4300 Glossary Unit DiagnosticPoint DataSection SetDry Ink PrintingIpds NormallyinstallationInitial IMLRadiation KanjiLight NUp PrintingPica Output StackerStorage ElementScan Print ModePortrait ArasterSystem/370 LinkSense Byte Sense DataBibliography Acronyms AbbreviationsIndex Numerics LAN FontsPrint Page Comments Readers Comments Wed Like to Hear from YouBoulder Readers Comments Wed Like to Hear from You