Q-Logic 59244-00 A manual Backup the Switch Configuration, Inventory Feature Licenses

Page 2

SANbox 9000Series Chassis Replacement Guide

A

Backup the Switch

Configuration

Create a backup of the switch configuration if one does not already exist and upload it from the switch to the management workstation.

Open a Telnet session and enter the

Config Backup command to create the file on the switch. Then use FTP to upload it to the management workstation. You can accomplish the same task using the Archive function of the QuickTools interface.

Switch login: admin

Telnet

Password: password

 

Sanbox #> admin start

Sanbox (admin) #> config backup SANbox (admin) #> exit

=======================================

ftp <ip_address>

FTP

User: images

 

Password: images

 

ftp> binary

 

ftp> get configdata

 

ftp> bye

 

Inventory Feature Licenses

Enter the Feature Log command to display the installed feature licenses. Make note of the license keys so that the feature licenses can be installed in the new chassis.

If you have installed license keys, enter the Show Version command and make note of the chassis serial number. You will need this number to request new license keys later.

SANbox #> feature log Mfg Feature Log:

----------------

Customer Feature Log:

---------------------

1)day mon date hh:mm:ss year - Switch Licensed for HyperStack(tm)capability

200000-LCRXIET7KXSXO

SANbox # > show version

*****************************************************

* *

* Command Line Interface SHell (CLISH) *

* *

*****************************************************

SystemDescription SANbox 9000 FC Switch EthNetworkAddress 10.20.11.192 (use 'set setup system EthMACAddress 00:c0:dd:00:71:ee

WorldWideName 10:00:00:c0:dd:00:71:ed

ChassisSerialNumber FAM033100024 SymbolicName SANbox ActiveSWVersion V6.2.x.x.xx.xx ActiveTimestamp day month date time year DiagnosticsStatus Passed

Power Down the Switch

Isolate the switch from the fabric.

Confirm that the primary CPU Heartbeat LED is showing the normal 1 blink per second. This allows the switch to correctly report power supply status.

Move the On/Off switch to the Off position on both Power Supply blades.

Unfasten the restraint bails from the plugs, and unplug the power cords from both Power Supply blades.

1

1. Heartbeat LED

2

59244-00 A

Image 2
Contents SANbox 9000 Series Chassis Replacement Guide Tools RequiredPower Down the Switch Backup the Switch ConfigurationInventory Feature Licenses Remove I/O Blades Disconnect Ethernet and Serial CablesDisconnect Fibre Channel Port Cables Remove CPU Blades Remove Power Supply BladesRemove the Fan Blades Prepare the New Chassis Remove Chassis from the RackRemove Brackets and Rails Reinstall Fan Blades Install New Chassis RackReinstall CPU Blades Power Up the Switch Reinstall Power Supply BladesReinstall I/O Blades Reconnect Ethernet and Serial CablesVerify the Post Results Reinstall License KeysObserve Heartbeat LED