Emerson Process Management MICRO, GFC manual Loop Supply Wiring, Field I/O Wiring Considerations

Page 15

2.2 LOOP SUPPLY WIRING

Loop Supply’s utilize Terminal Blocks that are equipped with compression-type terminals which accommodate a #16 AWG size wire. A connection is made by inserting the wire’s bared end (1/4” Max.) into the clamp beneath the screw and then tightening the screw. Three Loop Supply Terminal Blocks accommodate wiring as follows:

TB1 – Typically interfaces Bulk Power Input (May be used for Bulk Power Pass-through)

TB1-1

– VIN

(9-30V Bulk Power Input)

TB1-2

– GND

(9-30V Bulk Power Return)

TB1-3

– EARTH

(CHASSIS Ground)

TB2 – 24Vdc Loop Power

 

TB2-1, 3, 5,

7

– 24V

(Regulated +24V)

TB2-2, 4, 6,

8

– 24VRET

(Regulated 24V Return)

TB3 – Typically interfaces Bulk Power Pass-through (May be used for Bulk Power Input)

TB3-1

– EARTH

(CHASSIS Ground)

TB3-2

– GND

(9-30V Bulk Power Return)

TB3-3

– VIN

(9-30V Bulk Power Input)

Field I/O Wiring Considerations

Regardless of the ControlWave RTU type in question, Loop Supply wiring will only be utilized in conjunction with non-isolated I//O. Refer to Fig. 4 or 5 for applicable RTU wiring assignments.

In the case of ControlWave Express, ExpressPAC and GFCs, non-isolated AI and AO are available but, depending on the Input Voltage type, the unit’s AI/AO will be internally or externally powered. For 24Vdc powered RTUs AI/AO loop power will typically be sourced directly from the unit’s associated bulk power supply input. For 6V or 12V (dc) powered RTUs, both the non-isolated AI and non-isolated AO loop power may be provided by the Loop Supply’s regulated 24Vdc power output via the EXT POWER Terminal (TB7-3) and GND terminal (TB7-4) on the Process I/O Board’s Analog Output Terminal Block.

Power Input and Pass-through Wiring Considerations

In some cases the same bulk supply that powers the Loop Supply Assembly may be used to power the RTU. The bulk source should be wired to TB1 of the Loop Supply and then to RTU’s power input terminal. If a Power Distribution Board is present, the bulk power source should be wired as follows:

First to Power Distribution Board Terminal Block TB1

Then from TB2 of the Power Distribution Board to TB1 of the Loop Supply Then from TB3 of the Loop Supply to the RTU’s Input Power Terminal.

Bulk power may be supplied from Loop Supply connector TB3 (pass-through) to one of the following RTU Input Power Terminals):

Controlwave MICRO – Power Supply/Sequencer Module (PSSM) - Connector TB1

TB1-1

= +VIN

(from loop Supply Connector TB3-3

= VIN)

TB1-2

= -VIN

(from loop Supply Connector TB3-2

= GND)

Page - 6

PIP-ControlWaveLS

Image 15
Contents Product Installation Guide IMPORTANT! Read Instructions Before Starting Warranty Mail Bristol IncPhone Bristol Inc. Repair Authorization Form off-line completion Training 860 860 945-2213 FAX Few Words About Bristol IncVisit our Site on the World Wide Web Training Courses PIP-ControlWaveLS General Description Loop Supply Component IdentificationTerminal Blocks TB1 TB3 Fuse F1 Regulated 24V Supply Distribution Connector TB2 Configuration Jumper JP1 Power LEDLoop Supply Mounting Loop Supply InstallationEncapsulated ControlWave Loop Supply Mounting Diagram Loop Supply Wiring Field I/O Wiring ConsiderationsPower Input and Pass-through Wiring Considerations ControlWave Micro & EFM Loop Supply to I/O Module Wiring = GND = Power IN+ Environmental Specifications Operating SpecificationsConnectors Part NumbersDiminsions Loop Supply Dimensions Drawing ControlWave Loop Power Supply