Chapter 2 Installation and Maintenance
Only trained service personnel should install and maintain the power supply.
Prior to installation, utility line voltage must be routed to the enclosure. Local, state, federal and/or National Electric Code (NEC) regulations regarding location, permits and electrical wiring must be adhered to.
Do not operate the power supply where the temperature and humidity are outside the specified limits. See Specifications in this manual.
Unpacking
Inspect the unit upon receipt. Notify the carrier if there is damage. The packaging is recyclable; save it for reuse or dispose of it properly.
Check the package contents. The package contains the enclosure and product documentation.
Models Supported
Model Number
CTFLEH150
CTFLEH500
Description
ENCL, CTFLE Series, 36”, Metered
ENCL, CTFLE Series, 50”, Metered
CTFLE Enclosure Installation
Ensure the utility circuit breaker is OFF.
1.Set the CTFLE near the installation site.
2.Remove the screws that secure the front panels and the top section on the enclosure.
3.Unlock the bottom panel. When unlocked this panel will drop off the CTFLE easily.
4.Lift the top section off the CTFLE.
5.Remove the CTFLE floor plate and use as a template to mark the locations for the mounting stakes.
6.Remove enough topsoil so that when installed, the enclosure will sit one inch below grade.
Note: Position the stakes so that the utility and coax | Cable |
| |
cables will enter through the bottom of the enclosure. | Cable |
|
4.Bolt the floor plate onto the stakes.
5.Set the enclosure on the floor plate and replace the bolts securing the CTFLE to the floor plate.
6.Install conduit over the utility and coax cables inside the CTFLE.
3