American Power Conversion 480kW manual Until Battery capacity Test Xxx Press Data stored

Page 30

Maintenance & Testing

Action

Display shows

1.Press

2.Press or

until

Battery capacity

test :

xxx

 

3. Press

Battery capacity

test :

ON

 

4. Press

Data stored

Description

"xxx" is back-up time from last test –

if no previous test has been performed or if the test has been aborted the display will read"???"!

A battery monitor test can be performed in the same way by selecting "Battery monitor test" in the display.

However, this test will not start, unless the battery is fully charged

The next step starts up the test! To abort press

Starts the battery test.

(To interrupt a running test – perform point 1-2 and then press key

and )

5.Wait about 1 sec.

6.Wait until backup times expires and a short alarm sounds. (No alarm in battery monitor test

if battery is OK)

7.Press

8.Press

Battery operation time : xxx min.

Normal operation load power xx%

Battery capacity

test : xxx

Normal operation load power xx%

"xxx" is obtained back-up time

in minutes. (Battery capacity test only)

Exits the parameter stack

If not operated the system will automati- cally exit after 30 seconds.

CAUTION!

To avoid battery damage, allow a minimum of 16 hours of UPS operation over a 3-month period for batteries to charge to a sufficient level.

If the UPS is to be taken out of operation for an extended period, disconnect the battery in order to prevent discharging. For details, refer to Installation Guide.

990-4058GB

30

User Guide APC Silcon 480kW 400/415V UPS

Image 30
Contents 480kW 400/415V UPS User Guide Copyright 2002 APC JapanUser Guide APC Silcon 480kW 400/415V UPS Thank YouContents Introduction IntroductionDisplay Unit Stop/Start UPS and Operating the External Service Bypass Stop UPS for stand-byStart UPS from stand-by Stop UPS for complete power down Switching off the UPSSystem OFF Start UPS from complete power down UPS start-upSystem start-up now completed Operating the External Service Bypass Switch single systems Bypassing the Single System UPSStop/Start UPS and Operating the External Service Bypass System OFF Normal operation Load power 0% Bypass operation Bypassing the Parallel UPS System All UPSs Press On the keyboard until Stop/Start UPS and Operating the External Service Bypass Set input switches Q001 to position Isolating one UPS in a Parallel/Redundant System Stop/Start UPS and Operating the External Service Bypass Operation OperationKeyboard Using the Remote Display Display of Measured ValuesEconomy Mode Parameter Settings Parameter SettingsParameter Settings Switching to Bypass Operation Programming KeysProgramming Example Normal operation Displaying the Alarm Stack Alarms and EventsAlarms and Events Mode CommentsPossible Alarms Alarms Description ActionAlarms and Events Rectifying Alarm Messages Parallel Operation AlarmsCorrection of false alarm situations during service Battery Monitoring Test Maintenance & TestingMaintenance & Testing Battery Capacity TestUntil Battery capacity Test Xxx Press Data stored Warranty WarrantyAPC Silcon UPS Limited Factory Warranty APC Corporate How to Contact APCHow to Contact APC APC Denmark