ADC HRM-238 L1 user manual Installation, Inspecting Your Shipment, Installing the HRM-238 Shelf

Page 13

LTPH-UM-1237-04

Installation

 

 

INSTALLATION

INSPECTING YOUR SHIPMENT

Upon receipt of the equipment:

Unpack each container and inspect the contents for signs of damage. If the equipment has been damaged in transit, immediately report the extent of damage to the transportation company and to ADC Telecommunications, Inc. Order replacement equipment, if necessary.

Check the packing list to ensure complete and accurate shipment of each listed item. If the shipment is short or irregular, contact ADC as described in “Appendix B - Product Support” on page 14. If you must store the equipment for a prolonged period, store the equipment in its original container.

INSTALLING THE HRM-238 SHELF

Install the HRM-238 in a CO equipment bay rack. If the CO rack is 19 inches wide, attach the short side of the mounting bracket to the HRM-238 shelf and use the long side of the mounting bracket to attach to the CO rack. If the CO rack is 23 inches wide, reverse the mounting bracket. Attach the long side of the mounting bracket to the HRM-238 shelf and use the short side of the mounting bracket to attach to the CO rack (Figure 6).

1Position the HRM-238 shelf in the CO rack. (See “Operational Capabilities” on page 2, and Figure 2 on page 2, Figure 3 on page 3, or Figure 4 on page 3 for recommended placement.)

2Align the HRM-238 shelf mounting brackets with the vertical mounting holes on the CO rack (Figure 6).

3Install the mounting hardware and secure.

Mounting bracket

Security bracket

Mounting bracket

AB

H0546-B

Figure 6. Shelf with Brackets Positioned for 19-inch Rack

INSTALLING FRAME GROUND AND BATTERY POWER

Perform the following steps to install the -48 Vdc battery to the HRM-238 shelf and to connect battery common ground (LGND) and frame ground (FGND). The HRM-238 shelf terminal block TB1 has two connection points for supplying redundant battery capability. Connect a -48 Vdc battery source to Terminal 1 (-48V_A) to supply voltage to the HRM-238 shelf (Table 2 on page 6). Connect another -48 Vdc battery source to Terminal 2 (-48V_B) to supply redundant voltage to the HRM-238 shelf. See Table 2 on page 6 for TB1 terminal block information.

HRM-238 List 1

July 21, 2004

5

Image 13
Contents Clei T1MFW004 HRM-238 List 1 HiGain Retrofit Management ShelfRevision History Inspecting Shipment Using this ManualInspecting Shipment Table of Contents List of Figures List of Tables OS Port P2 and P4 Alarm J13 and J14 PinoutsList of Tables Overview FeaturesApplication Operational CapabilitiesRecommended Network Setup for 3190 Type Shelves Management Cabling Connector Purpose Type Gender No. PinsInstalling the HRM-238 Shelf InstallationInstalling Frame Ground and Battery Power Inspecting Your ShipmentTerminal Block TB1 Installing Communication WiringFor 220 type mechanics Connect NMA WiringP1 and P6 NMA Connectors Connect to a Computer, Terminal, or Modem Connect to a LAN or Interconnect ShelvesAUX P3 and P5 Connectors Turning UP the System Identifying AlarmsInsert Fuse Verify Cabling Installing the Management UnitsSecure Cabling Physical Appendix a SpecificationsAppendix B Product Support Appendix C Abbreviations Appendix C Abbreviations FCC Compliance Certification and WarrantyTechnical Assistance World Headquarters