INSTALLATION
PRE-INSTALLATION
1.Make sure there is a 16 amp.
2. Fixed | plumbing is | recommended | for | |
the machine. | The | water inlet of | the | |
machine has a collar with3/4”parallel | ||||
internal threads. The water supply | ||||
point with an external 3/4” parallel | ||||
thread | should | be | available within1 |
WATER |
| MACHINE |
SUPPLY | REDUCER | WATER |
|
| INLET |
STOP |
|
|
LOCK |
|
|
1/2 | 3/4 |
|
meter of the machine’s location. |
3. Two options on the water inlet and drain |
pipe connection are shown. In case these |
possibilities do not exist for the drain pipe, |
please arrange an additional length of pipe. |
DRAIN |
PIPE |
WATER INLET |
WATER INLET |
DRAIN |
PIPE |
4.Please inform our service centre for installation and demonstration of the machine once the points mentioned above have been completed.
UNPACKING
1.Remove Carton.
2.Remove wooden base. Keep machine on floor or trolley.
3.Place the machine at the site at which it is to be installed.
4.Remove transit bolts.
5.Insert plastic caps provided into holes vacated and press till they click into place.
6.Remove packing from the bottom of the motor
7.Keep transit bolts carefully. They will be required in case you need to shift the machine again.
8.For shifting and
9.Keep packaging material carefully. It comes handy while shifting residence.
10.PLEASE DO NOT OPERATE THE MACHINE TILL TRANSIT BOLTS HAVE BEEN REMOVED.
4