Figure 7 – Pad Rods & Pad Assembly
Step 8: Referring to Figure 7, slide (5) Part B3 drum-arm rods into the hole of each of the remaining Part D clamps. Tighten finger tight only at this point. Use the diagram above for reference.
Step 9: Referring to Figure 8, note that Percussion Pad Part DX-8 (hi- top) has an extra port connection and a pressure switch/button, which is used to control “choke” (Tone-Mute) of cymbal 5 (pad 5). During drum play this switch can be pressed by the drummers’ finger to activate the feature. The DX-8 percussion pad is color coded purple and should be mounted on the right of the drum stand. Install each of the Part DX- 8/DX-5 Percussion Pad to the rod/clamp (B3/D) combinations. Tighten the screws when complete (do not over-tighten).
Switch
Figure 8 -Pad DX-8 (hi-top)
Copyright© 2003 Pacific Digital Corporation | Page 10 |