21.Position the receiver by passing the opening in the receiver over the hanger pipe (Figure 14A).

27. Use three 10-32 x 3/8” pan head screws and flat

washers (supplied) to secure the flange to the

blade (ordered separately) (Figure 16A). Repeat for

the four remaining blades.

28. Use the 10 round recessed holes in the motor hub

HANGER

BRACKET

OPEN

1-1/4" THREADED SIDE STUD

SW375

RECEIVER

CEILING COVER

Figure 14A

HANGER BALL

marked with “5” and install the

five blade

assemblies in accordance with Step 29.

 

10-32 x 3/8"

PAN HEAD SCREW

FLAT WASHER

FAN BLADE

22.Connect the black wire from the wiring harness to the black (hot) supply wire (Figure 6A). Connect the white wire from the wiring harness to the white (neutral) supply wire. Connect the green ground wires from the hanger bracket and the hanger ball to the supply ground wire. Use wire connectors (supplied).

23.Securely connect the wiring harness connector to the receiver connector, and connect the blue and yellow wires from the downrod to the blue and yellow wires from the receiver (Figure 6A).

24.Fold and position the wires into the space above the hanger ball and into the outlet box (Figure 14A).

25.Feed the wires and connectors through the open side of the hanger bracket, and into the outlet box. Slide the receiver up and over the hanger bracket. Press the receiver against the ceiling and hold it in place. Then lift the ceiling cover up to the threaded studs and turn until studs protrude through the holes in the ceiling cover (Figure 15A).

26.Secure the ceiling cover in place by sliding lockwashers (supplied) over the threaded studs and installing the two knurled knobs (supplied). (Figure 15A.) Tighten the knurled knobs securely until the ceiling cover fits snugly against the ceiling and the hole in the ceiling cover is clear of the downrod.

BLADE

FLANGE

Figure 16A

29.Attach one blade assembly to the motor hub using two 10-32 x 5/8” oval head screws (supplied) (Figure 17A). Do not tighten completely at this time. Install remaining blade assemblies in the same way. Gently snug all flange screws to the motor hub, working around the hub in a clockwise sequence. Next, securely tighten all flange screws, again working in a clockwise sequence. Failure to follow this procedure could result in fan wobble. This completes the blade installation.

30.Pass the connectors and the wires form the motor shaft through the washer (supplied) and position the washer over the motor shaft (Figure 17A).

MOTOR HUB

 

CEILING COVER

1-1/4"

LOCKWASHERS (2)

 

THREADED

 

STUD

 

KNURLED KNOB

 

Figure 15A

!WARNING

To avoid possible fire or shock, make sure that the electrical wires are completely inside the outlet box and not pinched between the ceiling cover and the ceiling.

BLADE FLANGE

10 - 32 x 5/8"

WASHER

MOTOR

 

 

OVAL HEAD SCREW

 

SHAFT

 

(2 Per Blade Assembly)

 

 

Figure 17A

8

Image 8
Contents Raphael / Raphael Safety Instructions Tools Needed for Assembly Unpacking InstructionsImportant Installation Information Electrical RequirementsSection a 120V Supply Supply Wires PAN Head Screw Flat Washer FAN Blade Collar Setscrew Section B See Section a Black RED Using the 5/64 hex wrench supplied, loosen Installation of the Decorative Support Rods Assembly Trouble Shooting Using Your Ceiling Fan AccessoriesMaintenance Repair Parts Listing