Refrigeration Piping

Figure 6. Example of

Pipe Support

1.Normally, any straight run of tubing must be supported in at least two locations near each end of the run. Long runs require additional supports. The refrigerant lines should be supported and fastened properly. As a guide, 3/8 to 7/8 should be supported every 5 feet, 1-1/8 and 1-3/8 every 7 feet; and 1-5/8 and 2-1/8 every 9 to 10 feet.

2.When changing directions in a run of tubing, no corner should be left unsupported. Supports should be placed a maximum of 2 feet in each direction from the corner.

3.Piping attached to a vibrating object (such as a compressor or compressor base) must be supported in such a manner that will not restrict the movement of the vibrating object. Rigid mounting will fatigue the copper tubing.

4.Do not use short radius ells. Short radius elbows have points of excessive stress concentration and are subject to breakage at these points.

5.Thoroughly inspect all piping after the equipment is in operation and add supports wherever line vibration is significantly greater than most of the other piping. Extra supports are relatively inexpensive as compared to refrigerant loss.

Figure 7.

Line Insulation

After the final leak test, refrigerant lines exposed to high or low ambient conditions should be insulated to reduce heat loss or gain and prevent the formation of flash gas in the liquid lines. Suction lines should be insulated with 3/4" wall Armstrong “Armaflex” or equivalent. Liquid lines should also be insulated with 1/2-inch wall insulation or better. The insulation located in outdoor environments should be protected from UV exposure to prevent deterioration of insulating value.

10

Image 10
Contents Table of Contents Nomenclature General Safety InformationInspection Compressor Module Specifications Hermetic Compressor Module Electrical DataScroll Compressor Module Electrical Data Dimensional Diagrams One Fan Top View End ViewCondensing Unit Placement Space and Location RequirementsCondensing Unit Rigging Condensing Unit RiggingRefrigeration Piping And Line Sizing Refrigeration Piping And Line SizingSuction Lines Refrigeration PipingSuction Line Risers Example Pipe Support Line InsulationLeak Detection And Evacuation Leak TestingEvacuation Field Wiring Refrigeration Charging Refrigeration ChargingCheck-Out & Start-Up Operational Checkout System BalancingPreventive Maintenance Preventive Maintenance Preventive Maintenance Replacement Parts Replacement Parts ListDiagram WiringWiring Diagram Start-up Checklist PipingRecord Page Page FlexPack