GE RINTERxxxPS(P) Relay Panel Installation, Install Interior, Power Supply, Wire Line Voltage

Page 2

DEH40212 Installation Instructions

CAUTION: Make sure all power is OFF before wiring.

Do not energize wiring until the unit is fully assembled.

Conform to all applicable codes.

RELAY PANEL INSTALLATION

Figure 1

Dimensions (A x B)

RINTER1212PS(P)

SWITCHED LIGHTING CIRCUITS

1.5" x 1.5" CROSSOVER WIRING CHANNEL (TOP AND BOTTOM) 2" TYP.

16.0" (406mm) x 16.5" (419mm)

RINTER2424PS(P)

22.5" (572mm) x 24.0" (610mm)

RINTER4848PS(P)

36.0" (914mm) x 24.0" (610mm)

Relay Capacities (C)

RINTER1212PS

12 RR7 relays

RINTER1212PSP

12 RR9 relays

RINTER2424PS

24 RR7 relays

RINTER2424PSP

24 RR9 relays

RINTER4848PS

48 RR7 relays

RINTER4848PSP

48 RR9 relays

DIN Rail Capacities

A

RELAYS

CLASS 2

RELAYS

 

LOW-VOLTAGE

 

 

WIRING SECTION

 

C

 

C

 

DIN RAIL

 

CIRCUIT BREAKER PANEL

RINTER1212PS(P)

One module

4.5" D

 

 

LINE-VOLTAGE WIRING SECTIONS

 

RINTER2424PS(P)

Two modules

 

 

 

 

5" WIDE

 

 

 

 

 

 

B

 

 

 

ILLUSTRATION NOT TO SCALE

 

 

 

 

 

 

 

 

RINTER4848PS(P)

Two modules

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

If you have purchased the ProSys II Lighting Control System

 

 

Install Interior

(the stand-alone system), the devices (panels, switches and

 

 

• Power Supply

clock) will be in self-install mode, which means that as soon

 

 

 

Attach the power supply to the frame (bottom of 12-relay

as they are connected to the network, they are operational

 

 

 

interior and left side of 24- or 48-relay interiors) and plug

and can communicate with each other.

 

 

 

 

 

 

 

the low-voltage connector to the terminal marked “POWER”

If you have purchased the ProSys LM Lighting Control System

 

 

 

as shown in Figure 1 above.

 

 

• Interior

along with the ProSys LM software, the devices will be in

 

 

 

 

 

Mount the interior in the tub and secure it to the studs with

software-install mode. This means that in order for them to

 

 

 

 

 

 

the hardware provided. Make sure that all line- and low-

function on the network you must:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

voltage wiring is confined to the appropriate areas.

• assign network addresses to the devices and

 

 

 

 

 

 

 

 

 

 

 

• bind network variables and message tags using your

 

 

Wire Line Voltage

network management tool.

 

 

 

 

 

 

Before making any connections to the relays, make sure that

 

 

 

 

 

 

 

 

Addresses and binding are necessary for the devices to function on

 

 

none of the load circuits are shorted. Wire from the circuit

 

 

breaker through each relay’s SPST output terminals, and from

the network. ProSys LM users please refer to the ProSys LM

 

 

 

 

there to the loads. Confirm that each circuit is wired to the

Software User Guide for instructions on installing devices.

 

 

 

 

 

 

relay specified in the drawings. Wire the power supply.

 

 

 

 

 

 

 

 

Rough-In Tub

Environment

32 to 131oF (0 to 50 oC), 0 to 95% relative humidity, stationary applications

Mounting

The tub should be level, plumb and rigidly installed with hardware sufficient to hold 100 lbs. (48kg). For flush-mount panels, the front flange should be flush with the final finished surface. For multiple panels, allow 14” minimum between panels for showbox cover clearance.

Pulling Wires

Route line-voltage wiring through the 2 12” knockouts in either the top or bottom of the tub. Route Class 2 low- voltage dataline from the remote switches or other controls through the 34” knockouts in either end.

Figure 2

 

 

115

NEU GRD

J2

VAC

 

 

 

GE Lighting Controls

 

 

 

RINTER2424PS

 

 

shown

2

Image 2
Contents Description LTG-CNTL in the USA and CanadaPower Supply Relay Panel InstallationInstall Interior Wire Line VoltageBe controlled Power UP and Test RelaysDocument Relay Wiring Test. PressWhere the panels in a group can be numbered from 00 to Dataline InstallationGE RLONWIREP-S4 Dataline Wire Specifications Panel AddressingPanel Testing and Troubleshooting Panel TestingGE Total Lighting Control GE Total Lighting Control Woodford Avenue, Plainville, CT