Vermont Castings Resolute Acclaim
Alcove Installations
Because of their restricted air flow and heat retention characteristics, specific construction requirements and special clearances apply to installations into alcoves. No stove or chimney connector heat shields are used in alcove installa- tions. Bottom heat shield requirements remain the same as for other installations.
ALCOVE INSTALLATION OF THE RESOLUTE ACCLAIM IS NOT PERMITTED IN CANADA.
Construction Requirements
Showing
Joist Shield (supplied by chimney manufac- turer)
Metal
Stud
ST504 |
Fig. 22 Cutaway perspective of alcove installation. |
1” air gap top and bottom, on both sides and back wall
Combustible facing may overlap metal studs by only 1”
7/16” Durock© (or equivalent)
R E S O L U T E
Acclaim
ST609
Existings |
| |
Combustible Framing | 24" | |
| 11" | |
Metal studs | Min. | |
support 7/16” |
| |
Durock© (or | 36" | |
equivalent) | ||
Min. | ||
ceiling | ||
| ||
| 14¹⁄₄" | |
| 48" Min. | |
| ST505 | |
Fig. 23 Reflected ceiling plan. |
|
Fig. 25 Alcove side section. |
|
| |
Ceiling support |
|
| |
package |
|
| |
extends 2” |
|
| |
below Durock© |
|
| |
(or equivalent) |
|
| |
ceiling |
|
| |
1” air gap, |
| 62" Min. | |
top, bottom, | 65" | ||
on both sides | to Alcove | ||
| |||
and back |
| Ceiling | |
wall |
|
| |
NOTE: From |
|
| |
62” to 65” |
|
|
36" Use recommended Max. floor protection
48" Min.
7/16” Durock© (or equivalent) spaced 1” off wood studs on noncombustible spacers
ST502
must be |
covered by a |
noncombus- |
tible material. |
ST610
Fig. 26 Front section: 65” minimum clearance to combus- tibles on front face. Combustible facing may overlap metal
Fig. 24 Floor plan. Sheetrock on front face butts to Durock© (or equivalent) alcove lining.
studs by only 1”. It should not extend below the height of the noncombustible ceiling.
16 | 2000893 |