Empire Products DV-25T-1, DV-35T-1 Requirements for Massachusetts, Clear of ALL Obstructions

Page 5

REQUIREMENTS FOR MASSACHUSETTS

For all side wall horizontally vented gas fueled equipment installed in every dwelling, building or structure used in whole or in part for residential purposes, including those owned or operated by the Commonwealth and where the side wall exhaust vent termination is less than seven (7) feet above finished grade in the area of the venting, including but not limited to decks and porches, the following requirements shall be satisfied:

1.INSTALLATION OF CARBON MONOXIDE DETEC- TORS.At the time of installation of the side wall horizontal vented gas fueled equipment, the installing plumber or gasfitter shall observe that a hard wired carbon monoxide detector with an alarm and battery back-up is installed on the floor level where the gas equipment is to be installed. In addition, the installing plumber or gasfitter shall observe that a battery operated or hard wired carbon monoxide detector with an alarm is installed on each additional level of the dwelling, building or structure served by the side wall horizontal vented gas fueled equipment. It shall be the responsibility of the property owner to secure the services of qualified licensed professionals for the installation of hard wired carbon monoxide detectors

a.In the event that the side wall horizontally vented gas fueled equipment is installed in a crawl space or an attic, the hard wired carbon monoxide detector with alarm and battery back-up may be installed on the next adjacent floor level.

b.In the event that the requirements of this subdivision can not be met at the time of completion of installa- tion, the owner shall have a period of thirty (30) days to comply with the above requirements; provided, however, that during said thirty (30) day period, a battery operated carbon monoxide detector with an alarm shall be installed.

2.APPROVED CARBON MONOXIDE DETECTORS. Each carbon monoxide detector as required in accordance with the above provisions shall comply with NFPA 720 and be ANSI/UL 2034 listed and IAS certified.

3.SIGNAGE.Ametal or plastic identification plate shall be permanently mounted to the exterior of the building at a minimum height of eight (8) feet above grade directly in line with the exhaust vent terminal for the horizontally vented gas fueled heating appliance or equipment. The sign shall read, in print size no less than one-half (1/2) inch in size, “GASVENTDIRECTLYBELOW. KEEP

CLEAR OF ALL OBSTRUCTIONS”.

4.INSPECTION. The state or local gas inspector of the side wall horizontally vented gas fueled equipment shall not approve the installation unless, upon inspection, the inspector observes carbon monoxidedetectors and signage installed in accordance with the provisions of 248 CMR 5.08(2)(a) 1 through 4.

(b)EXEMPTIONS: The following equipment is exempt from 248 CMR 5.08(2)(a)1 through 4:

1.The equipment listed in Chapter 10 entitled “Equipment Not Required To Be Vented” in the most current edition of NFPA 54 as adopted by the Board; and

2.Product Approved side wall horizontally vented gas fueled equipment installed in a room or structure separate from the dwelling, building or structure used in whole or in part for residential purposes.

(c)MANUFACTURER REQUIREMENTS - GAS EQUIPMENT VENTING SYSTEM PROVIDED. When the manufacturer of Product Approved side wall horizontally vented gas equipment provides a venting system design or venting system components with the equipment, the instructions provided by the manufacturer for installation of the equipment and the venting system shall include:

1.Detailed instructions for the installation of the venting system design or the venting system components; and

2.Acomplete parts list for the venting system design or venting system.

(e)A copy of all installation instructions for all Product Approved side wall horizontally vented gas fueled equipment, all venting instructions, all parts lists for venting instructions, and/or all venting design instruc- tions shall remain with the appliance or equipment at the completion of the installation.

13117-9-0907

Page 5

Image 5
Contents Installation Instructions Table of Contents Vent KIT Information Important Safety InformationLP-GAS Warning Odor Safety Information for Users of LP-GASClear of ALL Obstructions Requirements for MassachusettsIntroduction SpecificationsMethod of Installing a Tee Fitting Sediment Trap Installing a New Main Gas CockGAS Supply Locating Gas SupplyClearances Installation InstructionsLocation of Furnace Locating Wall OpeningAttaching Furnace to Wall Mounting Bracket Installing Wall Mounting BracketOn Sheet Rock Wall Using Plastic Expansion Anchors Reassembly And Resealing Vent-Air Intake System Installing Vent AssemblyPiezo Pilot Ignitor Instructions Thermostat LocationSystem Check Figure Lighting Instructions For Your Safety Read Before LightingPrimary Air Adjustment Figure Pilot Flame CharacteristicsMain Burner Flame Characteristics Troubleshooting MaintenanceParts List HOW to Order Repair PartsParts View Installing Optional DRB-1 Blower Optional Blower Installation InstructionsWiring Fan ControlIndex Part Description 2090 Motor CleaningOiling Service Notes