Empire Comfort Systems DV-55T-1 Installation Instructions, Locating Wall Opening

Page 9

INSTALLATION INSTRUCTIONS

Locating Wall Opening

The furnace is to be located on an outside wall. Locate wall studs so that wall opening will be located between wall studs. The furnace is 16 inches in width and normal 16 inches on center studs will not allow the furnace to be recessed into the wall unless a stud is repositioned. The wall opening required as shown in Figure 5 is a diameter of 7 1/2 inches.

A template is provided in furnace carton for positioning furnace on the wall. Also, refer to Figure 5 for positioning the furnace on wall and for locating gas line connection.

Installing Optional Side Outlets

Side outlet register, SOR-1 may be installed on one or both sides of the furnace at the required clearances of 18 inches to adjacent wall or combustible material as shown in Figure 4.

1.Locate and cut the 5 1/2" square opening in the cabinet side using the template from the kit, exposing the inner liner knock-out.

2.Remove the knock-out.

3.Place the register on the 5 1/2" opening with the louvers set for the desired direction and mark the mounting holes using the register as a template.

4.Drill two (2) 1/8" diameter holes in cabinet side and fasten the register in place with two (2) 10 x 1" screws provided.

Side outlet kit, 10" boot assembly with register, SOK-1 for warm air discharge into an adjoining room may be installed on either side of the furnace at the required clearance of 4 inches to adjacent wall as shown in Figure 7.

1.Locate and cut the 5 1/2" square opening in the cabinet side using the template from the kit, exposing the inner liner knock-out.

2.Remove the knock-out.

3.Using the inner and outer boots as hole templates, mark and drill eight (8) 1/8" diameter holes in the inner liner and cabinet side.

4.Using Figure 7 locate and cut a 6 3/4" square opening through walls.

5.Prepare wall opening for the vent-air intake system (see Locating Wall Opening).

6.With furnace in place, after checking alignment of side outlet opening in wall and furnace, place the 9 3/8" x 9 3/8" side outlet wall plate over outer boot, pass the outer boot through the wall and attach side outlet wall plate to furnace side of wall with two (2) 10 x 1" screws provided.

7.Fasten outer boot to the cabinet side with four (4) 8 x 1/4" screws provided.

8.Position and attach inner boot to inner liner with four (4) 8 x 1/4" screws provided.

9.Locate the register with its louvers positioned for the desired air discharge direction and mark the mounting holes using the register as a template.

10.Drill two (2) 1/8" diameter holes in the wall and fasten the register in place with two (2) 10 x 1" screws provided.

Figure 5

Figure 6

Figure 7

13118-7-0408

Page 9

Image 9
Contents Installation Instructions Table of Contents Vent KIT Information Important Safety InformationLP-GAS Warning Odor Safety Information for Users of LP-GASClear of ALL Obstructions Requirements for MassachusettsIntroduction SpecificationsGAS Supply Installing a New Main Gas CockLocating Gas Supply FeetClearances Checking Manifold PressureClearances Installation Instructions Installing Optional Side OutletsLocating Wall Opening Using Plastic Expansion Anchors Installation of Three-prong Grounding Plug AssemblyInstalling Vent Assembly Reassembly And Resealing Vent-Air Intake SystemInstallation Instructions Or explosion Lighting InstructionsMain Burner Flame Characteristics Pilot Flame CharacteristicsThermostat Installation WiringService & Maintenance Suggestions Parts List HOW to Order Repair PartsParts View Service Notes Service Notes Comfort Systems