Lennox International Inc Gas Packaged Units Drip Leg Installation, Pressure Test Gas Piping

Page 11

Drip Leg Installation

field provided

 

1/8 in. pressure tap

 

ground joint

unit

union

manual main

 

shut−off valve

 

 

drip

 

leg

 

gas piping

 

support

Figure 8

Pressure Test Gas Piping

When pressure testing gas lines, the gas valve must be disconnected and isolated. Gas valve can be damaged if subjected to more than 0.5 psig (14 inch w.c.). See figure 9. If test pressure is equal to or less than 0.5 psig (14 inch w.c.) shutoff the manual main shut-off valve before pressure testing to isolate unit from gas supply system.

Isolate Gas Valve To Pressure Test

Manual Main Shut−off Valve Will Not Hold Test Pressures in Excess of 0.5 PSIG (14 in. w.c.)

unit

 

gas valve

cap

 

Figure 9

NOTE − Codes may require that manual main shut off valve and union (furnished by installer) be installed in gas line external to unit. Union must be of the ground joint type.

!WARNING

Danger of explosion. Can cause injury or product or property damage. Do not use matches, candles, flame or other sources of ignition to check for leaks.

After gas piping is complete, carefully check all piping connections (factory and field) for gas leaks. Use soap solution or other preferred means.

NOTE − In case of emergency shutdown, shut off main manual gas valve and disconnect main power to unit. These devices should be properly labeled by installer.

The heating value of the gas may differ with locality. The value should be checked with the local gas utility.

NOTE − There may be a local gas utility requirement specifying a minimum diameter for gas piping. All units require a 1/2 inch pipe connection at the gas valve.

Gas piping recommendations:

CAUTION

If a flexible gas connector is required or allowed by the authority that has jurisdiction, black iron pipe shall be installed at the gas valve and must extend outside the cabinet. The flexible connector can then be added between the black iron pipe and the gas supply line.

1 − A drip leg and a ground joint union must be installed in the gas piping.

A ground joint union is recommended by the manifold/valve.

2 − When required by local codes, a manual shut-off valve may have to be installed outside of the unit.

3 − Use pipe thread sealing compound resistant to propane gas sparingly on male threads.

4 − The gas supply should be a separate line and installed in accordance with all safety codes. After the gas connections have been completed, open the main shut-off valve admitting normal gas pressure to the mains. Check all joints for leaks with soap solution or other material suitable for the purpose.

CAUTION

Some soaps used for leak detection are corrosive to certain metals. Carefully rinse piping thoroughly af- ter leak test has been completed. Do not use matches, candles, flame or other sources of ignition to check for gas leaks.

5 − The unit and its individual manual shut-off valve must be disconnected from the gas supply piping system during any pressure testing of that system at test pressures in excess of 1/2 PSIG (3.48kPa).

IMPORTANT

The unit must be isolated from the gas supply piping system by closing its individual manual shut−off valve during any pressure testing of the gas supply piping system at test pressures equal to or less than 1/2 psig. See figure 9.

The unit and its individual shut−off valve must be dis- connected from the gas supply piping system during any pressure testing of the system at test pressures greater than 1/2 psig.

6 − A 1/8 inch N.P.T. plugged tapping, accessible for test gage connections, must be installed immediately upstream of the gas supply connection to the furnace.

Page 11

Image 11
Contents Retain These Instructions For Future Reference Table of ContentsLbs 15GCSX Unit Dimensions − inches mmShipping & Packing List Safety Information GeneralParts Arrangement Location Selection Clearances Rigging & Setting UnitAccessory Lift Kit Service Clearances − Inches MillimetersExisting Common Vent Systems Vent Hood InstallationVent Hood Installation Page Typical Condensate Drain Condensate DrainFilters Air Opening Covers Supply & Return Duct ConnectionsUnit Filter Size Removing Supply and ReturnGas Heat Application Data Gas Piping and Electrical Conduit AccessCompressors Gas Supply and PipingGas piping recommendations Drip Leg InstallationPressure Test Gas Piping Isolate Gas Valve To Pressure TestThermostat 208/230 Line Voltage WiringHeat Anticipator Setting Electrical15GCSX Series Gas Packaged Units Typical Wiring Diagram Blower Control A54 Blower Control A54Cool Cooling Start−Up Honeywell VR8205 Series Gas Valve Heating Start−UpNormal Operating Pressures Heating Sequence of Operation Checking and Adjusting Gas InputPost Start−up Check List Gas High Altitude InformationIgnition Control A3 Blower Delay − HeatingUnit Controls Blower Control A54Ignition Control LED Codes Pressure SwitchRollout Switch Ignition ControlSystem Operation Monitor A132 Comfort Alert Code Auto−Reset FunctionCondenser Fan Clearances System Operation Monitor LsomSystem Operation Monitor LED Troubleshooting Codes Planned Service MaintenanceRepair Parts & Accessories
Related manuals
Manual 4 pages 39.07 Kb

Gas Packaged Units, 15GCSX specifications

Lennox International Inc. is a leading name in the HVAC industry, renowned for its innovative and energy-efficient products. Among its featured offerings are the 15GCSX Gas Packaged Units, specifically designed to provide reliable heating and cooling performance for residential and light commercial applications.

The 15GCSX models stand out with their impressive efficiency ratings, achieving up to 14 SEER (Seasonal Energy Efficiency Ratio) for cooling and 81% AFUE (Annual Fuel Utilization Efficiency) for heating. This ensures that users can enjoy a comfortable indoor environment while also managing energy costs, making them an environmentally friendly choice.

One of the key features of the 15GCSX is its compact design, allowing for easy installation in tight spaces. This is particularly beneficial for urban settings where space can be at a premium. The unit’s all-in-one design integrates both heating and cooling capabilities, eliminating the need for separate systems and simplifying maintenance.

The 15GCSX Gas Packaged Units utilize advanced technologies to optimize performance. Equipped with Lennox’s proprietary iComfort technology, these units can connect to smart thermostats, allowing users to monitor and adjust settings remotely. This innovation enhances energy savings and provides users with full control over their indoor climate, contributing to enhanced comfort levels.

In terms of durability, the 15GCSX models feature a robust construction, complete with weather-resistant cabinet materials designed to withstand the elements. The unit’s stainless steel heat exchanger is built for longevity and efficiency, further enhancing the overall reliability of the system.

Noise reduction is another critical consideration in the design of the 15GCSX units. They come equipped with a specially designed, quiet-running fan and compressor that help to minimize operational sound levels, ensuring a peaceful indoor environment during use.

In conclusion, the Lennox 15GCSX Gas Packaged Units represent a high-quality solution for efficient heating and cooling needs. With their combination of advanced technology, energy efficiency, compact design, and durability, these units are an excellent choice for homeowners and businesses seeking reliable climate control. The integration of smart features and silent operation further solidifies their position as a preferred option in the HVAC market.