Weil-McLain GV Series 4, GV Series 3 manual Vent

Page 7

GOLD GV Series 3 & 4 — Z-Vent II Venting Supplement

Installation — assembly continued

Figure 8 Sidewall termination installation (non-direct venting)

¼ " to ¾ " between stop on termination and metal plate

Spacers (2)

(to support and center vent in sleeve)

 

Pipe section

 

4" galvanized sleeve

 

(through 4¹⁄₈" hole for

 

combustible wall)

 

Metal plate

Metal plate

Spacers (2)

 

(to support and

 

center vent in

 

sleeve)

 

Pipe section

 

 

 

Sealant

Sealant

 

 

 

 

 

Termination coupling

26609

Figure 9

Non-direct vent through sidewall

Figure 10

Non-direct vent through roof

(using termination coupling) Follow Z-Vent II manufacturer’s instructions for proper installation of vent runs, including slope and support.

Follow Z-Vent II manufacturer’s instructions for proper installation of vent runs, including slope and support.

Z-Vent II

vent starter tee

 

Z-Vent II

 

vent starter tee

26604b

26605b

Part number 550-110-266/0601

7

 

Image 7
Contents Hazard definitions To the installerAreas likely to have contaminants Combustion air supplySpecial note Products to avoidVenting method definitions Vent terminationProperly locate vent termination Pre-installation planning InstallationDescription Flex , Inc Part Number Note Slope Select vent methodConnect vent run to termination Installation assemblyConnect vent starter tee to boiler Construct vent and optional combustion air runVent Installing condensate tubing Finish the vent installationIf vent pipe or combustion air pipe must be reassembled