Nortec RESDELUX manual Figure #3 Wall Mounting Detail

Page 5

Figure #3

Wall Mounting Detail

nozzle will have to be mounted from the inside of the duct. Remove internal insulation material if necessary. (See Figure #5).

Wall

Fasten Humidifier To

Wall Using Screws 2” long

(2) supplied by other

0.6”

(1.6 cm)

12.1” A(30.7cm)

Figure #5

Steam Distribution Nozzle Mounting Arrangement

5.Make sure humidifier is level.

6.DO NOT mount humidifier on hot surfaces.

7.DO NOT mount humidifiers in an area where freezing may occur.

8.DO NOT mount humidifiers on a vibrating surface.

10.DO NOT mount the humidifier to a duct or plenum.

STEAM DISTRIBUTOR NOZZLE (in duct location)

3.When the steam distribution nozzle is located above the top surface of the humidifier: The nozzle must be at least 1 ft (305 mm) above the top surface of the humidifier. Locate the steam hose so that it slopes at an angle of at least 20° (Figure #6).

Figure #6

Steam Plumbing Arrangement Above Humidifier

1.When installing the steam distribution nozzle of the RESDELUX humidifier it must be located in the supply duct at least 4 feet from any obstructions such as bends, fans, filters, etc. to prevent wetting (see figure #4).

Figure #4

Steam Distributor Nozzle in Duct Location

 

min. 2º

 

 

 

min. 10º

mm)

 

Rmin

.

(300

mm)

min. 10º

 

 

(300min.12”

12”

 

mm)(30012”

 

 

 

Min. 12”

 

(150

mm)

min

 

 

 

6”

 

 

To be 2” (50mm) longer then duct static pressure or minimum.

Nortec

Humidifier

NHB, NHP, NHMC,

RESDELUX ONLY

2.The steam distribution nozzle can be mounted in the bottom wall or on the vertical walls of the duct. If the duct wall is more than 3/4" (20 mm) thick, the

4.Steam distribution nozzle below top surface of humidifier: The steam hose must first rise to the minimum height of 1 ft (305 mm) above the top surface of the humidifier and thereafter slope a minimum 5￿ in a uniform manner toward the nozzle. A separate drain line must be provided for condensate that collects at the steam distribution nozzle (Figure #7).

- 2 -

Image 5
Contents Installation, Operation Maintenance Troubleshooting Guide Table Of Contents Page PRE-INSTALLATION Checkpoint InstallationHumidifier Configuration Receiving & Unpacking EquipmentFigure #3 Wall Mounting Detail Blower Pack Connection Steam Hose InstallationFigure #9 Blower Pack Cabinet Assembly Drain Line PlumbingWater Supply Line Page Resdelux Operation OperationIntroduction Manual Capacity Adjustment MaintenanceWhen to Replace the Steam Cylinder Steam CylinderHOW to Install the Replacement Cylinder HOW to Remove the Steam CylinderExtended Shutdown Mandatory Cleaning of the Drain ValveDiagnostic Procedures Troubleshooting TroubleshootingProcedures and Terms Used Diagnosing Page Page Item Number Part Number Description Spare Parts List and Exploded View Resdelux21a 21b 21c 13a 13d 13e 13b 13c 11b 11a 12 12a 14a Inspect, Check, Clean, and Adjust all items listed Periodic Maintenance ChecklistLimited Warranty MTH/DAY/YR