State Industries GS675YRVLT Horizontal Vent Clearances, Planning the Vent System

Page 16

U.S. HORIZONTAL VENT CLEARANCES

WARNING

VENT HOOD(S) MAY BE

EXTREMELY HOT

DURING OPERATION.

FIGURE 15.

2.A venting system should terminate at least 3 feet above any forced air inlet located within 10 feet.

3.The venting system should terminate at least 4 feet below, 4 feet horizontally from or, 1 foot above any door, window or gravity air inlet into any building.

4.The manufacturer also recommends that the vent system termination not be installed closer than 18” from an inside corner of an L shaped structure and not be less than 1 foot above grade. The vent should terminate a minimum of 12’’ above expected snowfall level to prevent blockage of vent termination.

5.The vent termination should not be mounted directly above or within 3 feet horizontally from an oil tank vent or gas meter to avoid potential freeze-up from condensation.

Plan the vent system layout so that proper clearances are maintained from plumbing and wiring.

Vent pipes serving power vented appliances are classified by building codes as “vent connectors”. Required clearances from combustible materials must be provided in accordance with information in this manual under LOCATION OF HEATER and INSTALLATION OF VENT SYSTEM, and with the National Fuel Gas Code and local codes.

PLANNING THE VENT SYSTEM

Plan the route of the vent system from the discharge of the blower to the planned location of the vent terminal.

1.Layout the total vent system to use a minimum of vent pipe and elbows. Take into consideration that an elbow will be necessary to make the first vent pipe connection to the power venter outlet, see Figure 6.

2.This water heater is capable of venting the flue gases the equivalent of thirty (30) feet of 3 inch pipe or one-hundred (100) feet of 4 inch pipe as listed in Table 1.

TABLE 1.

Number of

3” Maximum

4” Maximum

90° Elbows

Pipe (Feet)

Pipe Feet

ONE (1)

25

92

TWO (2)

20

84

THREE(3)

15

76

FOUR (4)

10

68

FIVE (5)

- - -

60

Minimum of one (1) elbow and 2 feet of straight pipe must be installed for 3” and 4” pipe.

NOTE: The equivalent feet of pipe listed above are exclusive of the “45° Elbow” termination. That is, the termination “45° Elbow”, with installed screen, is assumed to be in the system and the remainder of the system must not exceed the thirty (30) equivalent feet of 3 inch pipe or one-hundred (100) equivalent feet of 4 inch pipe.

3.The blower discharge adapter is made to accept only straight sections of 3” pipe. To start a minimum of 2 inches of 3” pipe must be attached to the blower discharge. See Figure 6.

If using 3 inch vent pipe:

A minimum of 2 inches, maximum of 4 feet of 3” pipe must be attached to the blower before the first 3-inch elbow. After the first elbow add the additional venting required for the installation. The total system cannot exceed 30 equivalent feet of venting, where each elbow is equal to 5 feet of straight pipe.

If using 4 inch vent pipe:

Two inches of 3” pipe must be attached to the blower discharge. A 4” x 3” reducer is added and then up to maximum 4 feet of 4 inch pipe added before the first elbow. An additional 4” x 3” reducer and (1) foot of 3” pipe must be added to the end of the vent system before terminating into the 3” 45° elbow. The total system cannot exceed 100 equivalent feet of 4” venting, where each elbow is equal to 8 feet of straight pipe.

16

Image 16
Contents Whenever maintenance adjustment or service is required 197218-002Safe INSTALLATION, USE and Service Important DefinitionsGeneral Safety General Safety Table of Contents IntroductionBELOW. Keep Clear of ALL Obstructions Typical Installation Replacement Parts and Deliming ProductsMixing Valve Usage Locating the NEW Water Heater Facts to Consider About the LocationInsulation Blankets ALL AIR from Inside Buildings See ALL AIR from Outdoors See Figures 7, 8Chemical Vapor Corrosion Installing the NEW Water HeaterWater Piping Temperature-Pressure Relief Valve Valve and Pipe Insulation if suppliedGAS Piping with Flexible Connector Gas PipingFilling the Water Heater Sediment TrapsVenting Vent Pipe Termination Planning the Vent System Horizontal Vent ClearancesVent Hoods MAY be Extremely HOT During Operation Blower Assembly Installation CondensateInstallation of Vent System Vent Terminal INSTALLATION, SidewallPower Vent Wiring Schematic Installation of Vent SYSTEM, Sidewall Installation of Vertical Vent SystemVent Pipe Preparation Recommended BRUSH* Size for Primer Cement ApplicationsStep B Step EStep F Step GPower Before Servicing Do not try to light the burner by handWhat to do if YOU Smell GAS Do not TRY to Light the Burner by HandTemperature Regulation Temperature SettingStart UP Conditions For Your InformationOperational Conditions Periodic Maintenance Burner CleaningVenting System Inspection Burner Operation and InspectionAnode ROD Inspection Temperature-Pressure Relief Valve OperationDraining Service Leakage CheckpointsRepair Parts List Propane Burner Assembly Natural GAS BurnerTroubleshooting Guidelines Trouble ShootingBurner flame, ensure flame is steady see #8 below Troubleshooting Guidelines Page Page Conditions and Exceptions Important InformationTennessee Waltz Parkway Ashland City, TN