DESCRIPTION OF OPERATION

1.The normal “ready” state of the system is as follows:

The material supply line is filled with dispensable material.

The system has been purged, filling the valve with material up to the Piston(4).

The Piston (4) is seated in the Needle Seat (1).

2.The dispense cycle begins when the controller is activated. Air at 70 psi (4.8 bar) enters the Open port and raises the Piston (4) off the Needle Seat (1).

3.Material flows through the Valve Body (5) and out through the Needle Block (23). Volume can be varied by changing the material pressure, needle size, dispense speed and dispense time.

4.When the correct amount of material has been dispensed, the controller relieves air from the Open port and applies air to the Close port. The Piston (4) seats back into the Needle Seat (1), sealing the valve and ending the dispensing process. The system is again in the normal “ready” state.

4

Image 4
Contents Dispensit Periodic Maintenance Safety Information General AccessoriesGeneral Information Illustration ReferencesDescription of Operation Setup Procedure Operating ProceduresMounting Dispense Valve AIR ControllerMaterial Loading Operation AdjustmentsWET System Checkout Dispense Needle Replacement Periodic MaintenanceDisassembly Model 710 General Illustration Assembly Troubleshooting Model 710 Recommended Spare Parts Quantity Description Part NumberGeneral Guidelines for O-RINGS and U-CUP Seals Ring GuidelinesPage Minneapolis Belgium, China, Japan, Korea