Graco 710 Material Loading, WET System Checkout, Operation Adjustments

Page 6

OPERATING PROCEDURES

MATERIAL LOADING

Material is supplied from a pressure vessel or pump with enough pressure to cause a proper rate of flow from the dispense needle. (Note: The material pressure will vary depending on the application.)

Warning: Do not apply either operating or reservoir air pressure to the product unless all screws are in place and properly tightened and all material supply connections are properly in place and tightened. Fasten all air connections securely.

Attach the air line to the regulator and set the air pressure control to the setting required for the application. (Note: When using a remote reservoir, the delivery tubing and fittings must be compatible with the material being dispensed and capable of withstanding the dispensing pressure.)

WARNING: Do not exceed 100 psi (6.9 bar) pressure on the operating system. Do not exceed 1200 psi (82.7 bar)

material inlet pressure. Higher pressures may cause a hazard or serious injury. Note: The minimum recommended pneumatic operating system pressure is 70 psi (4.8 bar) clean/dry air.

WET SYSTEM CHECKOUT

Using the purge cycle on the air supply controller, run the material through the material supply line and valve until a smooth material flow is observed through the dispense needle.

After the purge cycle has been completed, set the air supply controller to the manual cycle mode and cycle the dispense valve several times.

OPERATION ADJUSTMENTS

AIR SUPPLY ADJUSTMENT

The air pressure to the controller and material supply regulator is typically 70 psi (4.8 bar). Do not exceed 100 psi (6.9 bar) pressure to the dispense valve. However, the material supply pressure must be adjusted according to the type of material being dispensed. Too low a pressure will give you an inconsistent dispensed volume because the material does not have sufficient pressure to flow smoothly through the needle. Too high a pressure may cause material separation or packing. Use the minimum pressure needed to obtain smooth material flow during the purge cycle.

MATERIAL OUTPUT ADJUSTMENT

The material output depends on the material pressure, size of needle, and the rate at which the dispense valve is moved by the system to which it is attached.

Note: The Adjustment Screw (27) is used to adjust the maximum height setting of the Piston Rod (4) to the Needle Seat (1) and is not intended to be used as a flow control adjustment. See the Dry System Check (seen on the previous page) for more information.

DISPENSE NEEDLE HEIGHT ADJUSTMENT

Ideally, the material should just contact the work piece enough to create an adhesive bond and cause a clean separation of the material from the needle tip upon completion of the dispense cycle.

6

Image 6
Contents Dispensit Periodic Maintenance General Information Safety InformationGeneral Accessories Illustration ReferencesDescription of Operation Mounting Dispense Valve Setup ProcedureOperating Procedures AIR ControllerOperation Adjustments Material LoadingWET System Checkout Periodic Maintenance Dispense Needle ReplacementDisassembly Model 710 General Illustration Assembly Troubleshooting Model 710 Recommended Spare Parts Quantity Description Part NumberGeneral Guidelines for O-RINGS and U-CUP Seals Ring GuidelinesPage Minneapolis Belgium, China, Japan, Korea