Jackson JPX-300L, JPX-300HC, JPX-300HN operation manual Electrical Installation Instructions

Page 15

SECTION 2: INSTALLATION/OPERATION INSTRUCTIONS

ELECTRICAL INSTALLATION INSTRUCTIONS

SHOCK ABSORBER: It is also recommended that a shock absorber (not supplied with the JPX-300 series models) be installed in the incoming water line. This prevents line hammer (hydraulic shock), induced by the solenoid valve as it operates, from causing damage to the equipment.

CONNECTING THE DRAIN LINE: The JPX-300 series machines are a pumped (pressure) drain capable of pumping waste water to a height of 24 inches from the floor to the kitchen’s drain system. The dishmachines are supplied with a 10 foot long hose that extends from the rear side of the machine. There must also be an air gap between the machine drain line and the floor sink or drain. If a grease trap is required by code, it should have a flow capacity of 12 gallons per minute.

PLUMBING CHECK: Slowly turn on the water supply to the machine after the incoming fill line and the drain line have been installed. Check for any leaks and repair as required. All leaks must be repaired prior to placing the machine in operation.

ELECTRICAL POWER CONNECTION: Electrical and grounding connections must comply with the applicable portions of the National Electrical Code ANSI/NFPA 70 (latest edition) and/or other electrical codes.

Disconnect electrical power supply and place a tag at the disconnect switch to indicate that you are working on the circuit.

The dishmachine data plate is located on the front of the machine. Refer to the data plate for machine operating requirements, machine voltage, total amper- age load and serial number.

To install the incoming power lines, remove the kick panel. This will require tak- ing a phillips head screwdriver and removing the two screws at the bottom of the kick panel; open the door slightly while carefully lifting the kick panel up and out of the way. Install 3/4” conduit into the pre-punched holes in the back of the control box. Route power wires and connect to power block and ground- ing lug. Install the service wires (L1 and L2) to the appropriate terminals as they are marked on the terminal block. Install the grounding wire into the lug provided. It is recommended that “DE-OX” or another similar anti-oxidation agent be used on all power connections.

Ground Lug

Terminal Block

Control Box Electrical Connection

VOLTAGE CHECK: Ensure that the power switch is in the OFF position and apply power to the dishmachine. Check the incoming power at the terminal block and ensure it cor- responds to the voltage listed on the data plate. If not, con- tact a qualified service agency to examine the problem. Do not run the dishmachine if the voltage is too high or too low. Shut off the service breaker and mark it as being for the dishmachine. Advise all proper personnel of any prob- lems and of the location of the service breaker. Replace the control box cover and tighten down the screws.

Brass Plug

Rinse Aid Fitting

CHEMICAL CONNECTIONS: All chemical hookup loca- tions are located on the back of the dishmachine. Please refer to the drawing at the right for the correct connection point. The JPX-300H/HC/HN dishmachines are supplied with integral detergent and rinse aid chemical feeder pumps. The JPX-300L dishmachine is supplied with inte- gral detergent, rinse additive and sanitizer chemical feed- er pumps.

Detergent Fitting

Please refer to page 11 for instructions on priming the chemical feeder pumps.

Back of Unit Showing Chemical Connection Points

JPX-300 Installation/Operation Manual 7610-002-71-26 Rev. J

Issued: 03-09-2006 Revised: 9-14-2006

9

Image 15
Contents JPX-300HC JPX-300HN For Jackson ModelsONE Year Limited Parts & Labor Warranty Manufacturers WarrantyStop Pare Arret Revision Made Applicable Details Date ECN Nomenclature for the Models Covered in this Manual JPX-300HNTable of Contents Section Specification Information Specification Information Cuit breaker sizes as listed in the NEC 2002 Edition. Local Dimensions JPX-300H/HC DimensionsDoor Open JPX-300HN Dimensions AFF JPX-300L DimensionsSection INSTALLATION/OPERATION Instructions Installation Instructions INSTALLATION/OPERATION InstructionsElectrical Installation Instructions Chemical Dispensing Equipment To Prepare Chemical Feeder Pumps for OperationPriming Chemical Feeder Pumps JPX-300H JPX-300L Detergent Control Operation Instructions Operation Instructions /DELIMING Instructions Section Preventative Maintenance Preventative Maintenance Section Electrical Schematics JPX-300HN 115 Volt 60 Hertz Single Phase Electrical SchematicsElectrical Schematics Electrical Schematics JPX-300H/JPX-300HN 208-230 Volt 60 Hertz Single Phase Electrical Schematics Electrical Schematics Electrical Schematics JPX-300H 460 Volt 60 Hertz Three Phase Electrical Schematics Electrical Schematics JPX-300H Extended Wash 460 Volt 60 Hertz Three Phase Electrical Schematics JPX-300HC 208-230 Volt 60 Hertz Single Phase Electrical Schematics Electrical Schematics JPX-300L 115 Volt 60 Hertz Single Phase Electrical Schematics Electrical Schematics Electrical Schematics Section Jackson Maintenance Repair Centers Jackson Maintenance & Repair Centers AlabamaAlabama to Georgia Company Hawaii to MinnesotaMississippi to NEW York Nevada HI Tech Commercial ServiceElmer Schultz SVC North Dakota to UtahVermont to WYOMING/CANADA Canada