Machine Preparation
1.Park machine on a level surface and set brake.
2.Remove ROPS and hardware from shipping box and identify all parts using the parts list noted above.
Lower ROPS Leg Tube Installation
3.Jack and secure rear of mower and remove rear tires.
4.Remove left side rear fuel tank bracket bolts. Support tank.
5.Place LH leg weldment against LH machine frame mounting location.
6.Secure using (3)
7.Loosen high pressure hoses at the pump and swivel away from LH leg weldment.
Figure 1
8.Remove right side rear fuel tank bracket bolts. Support tank.
9.Repeat step
Figure 2